← Estimating, Costing & Valuation

Earthwork, Road & Canal Estimates

Computation of earthwork — longitudinal and cross sections, depth of cut and fill from formation levels; sectional areas of level sections in embankment and cutting; volume by mid-section (mean depth), mean sectional area (trapezoidal) and prismoidal formulas; mixed sections and transition points; lead and lift; road estimates (earthwork, pavement layers, shoulders, drainage, culverts, road furniture); canal estimates — sections in cutting, filling and partly cutting–partly filling, balancing depth; mass haul — with solved numericals.

📑 Contents (5 sections)

Last reviewed 16 Sept 2026 · 7 min read

Earthwork computation

Data

  • Longitudinal section (L-section) — ground levels (RL) at regular chainages (e.g. every 20 m or 30 m) along the centre line, with the proposed formation level (road/canal bed) fixed by gradient.
  • Cross-sections — ground levels across the centre line at each chainage.
  • Formation width, side slopes (cutting and filling), road/canal typical sections.

Depth at a section:

  • Embankment (filling): height formation level ground level (positive).
  • Cutting: depth ground level formation level.

Sectional area of a level section

FormulaLevel section (ground level across the section)

= formation width (top width of embankment or bottom width of cutting); = depth of fill or cut at the centre line; = side slope (horizontal : 1 vertical).

Volume between sections

FormulaEarthwork volume formulas (sections at distance L apart)

1. Mid-section (mean depth) method:

2. Mean sectional area (trapezoidal / average end area) method:

For a series of equally spaced sections:

3. Prismoidal formula:

( = area at the mid-section.) For a series with an odd number of equally spaced sections:

  • For level sections, the mean area method gives a slightly larger volume than the prismoidal formula (difference = prismoidal correction ); the mid-section method gives a slightly smaller volume.
  • The prismoidal formula is the most accurate for regular sections.

Mixed sections and transitions

  • Where the formation changes from embankment to cutting, the section at the transition point has zero depth; the chainage of the transition point is found by interpolation between adjoining sections of fill and cut.
  • Side-long (partly cut, partly fill) sections on sloping ground are computed as triangles/trapezoids for the cut and fill portions separately.

Lead and lift

  • Lead — horizontal distance over which excavated earth is carried, measured between the centres of gravity of excavation and deposit (or as specified).
  • Lift — vertical height through which earth is raised.
  • Schedule rates commonly include an initial lead of 50 m and lift of 1.5 m; extra lead and lift are paid additionally. Lifts may be converted to equivalent leads as per departmental rules.

Mass haul diagram

A plot of cumulative volume of earthwork (cuts positive, fills negative, corrected for shrinkage/bulking) along chainage, used to decide economic haul, borrow pits and spoil, free haul and overhaul (see Computation of Areas & Volumes).

This chapter is in the syllabus of

Open an exam to see where this chapter sits in its syllabus, and to practise it.

✅ Free — no sign-up needed