Project Crashing — Time-Cost Trade-off

Direct and indirect project costs; normal time and cost, crash time and cost; cost slope; total cost curve and optimum duration; steps of crashing a network — crashing critical activities in order of cost slope, parallel critical paths, new critical paths, stopping rules; fast tracking vs crashing; updating networks — with a fully worked crashing problem.

📑 Contents (8 sections)

Last reviewed 16 Sept 2026 · 6 min read

Project costs

Cost Meaning Behaviour when duration is reduced
Direct costs Costs directly attributable to activities — materials, labour, equipment for each activity Increase (overtime, extra shifts, more equipment, costlier methods)
Indirect costs Overheads — site supervision, office establishment, insurance, interest on capital, general administration, security; also penalties for delay (or bonuses) Decrease (roughly proportional to duration)

Total cost = direct cost + indirect cost — reducing the duration raises direct cost but lowers indirect cost, so the total cost curve has a minimum at the optimum duration.

Normal and crash points

  • Normal time () — duration under normal working conditions at the lowest direct cost (normal cost ).
  • Crash time () — minimum possible duration with maximum resources, at crash cost .
  • Reducing an activity below its crash time is impossible (or only increases cost without saving time).
FormulaCost slope

The extra direct cost per unit time saved (assuming a linear time–cost relationship between normal and crash points).