← Tunnel Engineering & Rock Mechanics

NATM & Tunnel Support

The principles of the New Austrian Tunnelling Method (NATM) — using the rock mass itself as the main load-bearing element — the excavation sequence, primary support elements (shotcrete, rock bolts, mesh, lattice girders and steel ribs, forepoling and pipe umbrellas), support classes from RMR or Q, rock load (Terzaghi), the convergence–confinement idea, and monitoring to control the support.

📑 Contents (8 sections)

Last reviewed 30 Sept 2026 · 9 min read

The idea behind NATM

The New Austrian Tunnelling Method (NATM), developed in the 1950s–60s by Rabcewicz, Müller and Pacher, is a design and construction philosophy rather than a single technique. Its central idea is that the rock mass around a tunnel is not just a load to be carried; it is the main load-bearing element. When a tunnel is excavated, the stresses in the rock redistribute around the opening and the rock deforms toward it. If the deformation is controlled, the rock can form a self-supporting ring, and only a thin, flexible support is required to control the deformation and to preserve the strength of the rock.

FormulaPrinciples of NATM
  1. Mobilise the strength of the rock mass — avoid damaging it (careful excavation) and let it carry the load.
  2. Support immediately, and flexibly — a thin shotcrete layer with bolts is placed soon after excavation, allowing controlled deformation — not too little (loosening and collapse) and not too much.
  3. Close the ring early — an invert closes the ring so that the support and rock act as a closed load-bearing tube; an open ring is unstable.
  4. Monitor — measure the deformation (convergence) and stresses to check the support behaviour; the support is adjusted according to the measurements (observational method).
  5. Adapt the design to the ground — support classes are matched to the ground types met, and a flexible contract allows changes.
  6. Sequence the excavation to keep the exposed span small and stable: heading, bench and invert with limited round lengths.

Convergence–confinement idea

The interaction between the rock and the support is described by the convergence–confinement method. As the face advances, the rock at the tunnel boundary moves inward (convergence) and its internal pressure on the opening decreases from the in-situ stress toward a lower value (the ground reaction curve). A support installed at some convergence has its own stiffness (the support characteristic) and the equilibrium is the point where the two curves meet.

  • Too early or too stiff a support attracts a high load.
  • Too late allows the rock to loosen and the load increases again (loosening pressure).
  • The best support is installed at the right time with a suitable stiffness, so that the equilibrium pressure is low.

This is why NATM uses flexible shotcrete and controlled deformation instead of a rigid, heavy lining installed at once.

Excavation sequence

  • Full-face in good ground; top heading and bench in fair ground; top heading, bench and invert with a short round length in poor ground; sidewall drifts in very poor ground.
  • Round length (advance per round) is small in poor ground — 0.8–1.5 m — and large in good ground (3–4 m).
  • Ring closure — the invert is closed within a short distance from the face (often one to two tunnel diameters) in weak ground, to stop the deformation.
  • Face stability — face bolts, a face core (a wedge of ground left at the face), shotcrete on the face, forepoling or a pipe umbrella ahead.

Support elements

Shotcrete

Shotcrete is concrete sprayed at high velocity onto the rock surface, building up a layer that bonds to the rock. It gives early support, fills irregularities, seals the rock against weathering and transfers load.

  • Types: wet-mix (the standard, more consistent and less dust) and dry-mix.
  • Thickness: 50–100 mm for good rock, up to 200–300 mm in weak ground (built up in layers).
  • Reinforcement: wire mesh or steel fibres (about 30–40 kg/m³) to control cracks and to provide toughness; synthetic fibres in some cases.
  • Accelerators give a rapid set and strength gain: early-age strength (at 3–24 hours) is critical when the shotcrete is loaded soon after application.
  • Properties: strength of 25–35 N/mm² at 28 days (or more); good bond to the rock; low rebound (material that bounces back).
  • Application: by a shotcrete robot, in layers, with attention to the nozzle distance and angle and to filling behind reinforcement.

Rock bolts

Rock bolts reinforce the rock mass by tying the loosened blocks to the rock behind and creating a supporting zone.

Bolt Description
Mechanically anchored (expansion shell) Anchored at the end; immediate support; often used for temporary support
Fully grouted (resin or cement) rebar Bonded over the full length; the standard in permanent rock reinforcement
Friction bolts (Swellex, split-set) Expand against the borehole wall; immediate load-bearing; used for temporary support
Self-drilling (hollow bar) Drilled and grouted in one step; suitable for loose or collapsing holes
Cable bolts Long, for large openings and deep-seated support
  • Length: commonly about a third to a half of the span for the roof; for a tunnel of span the Q-system gives m.
  • Spacing: typically 1–2 m in both directions; the spacing should be less than half the bolt length so that the bolts interact and form a reinforced arch.
  • Pull-out tests are made on a percentage of bolts to check the capacity.

Wire mesh, lattice girders and steel ribs

  • Wire mesh (welded) reinforces the shotcrete and holds small loose rock.
  • Lattice girders — light three-bar trusses, embedded in the shotcrete — provide early stiffness with less material and easier bonding than solid steel ribs; the standard in NATM.
  • Steel ribs (HEB sections or TH profiles) — used in weak or squeezing ground; sliding joints (TH type) allow controlled closure. Ribs are embedded in shotcrete (rib–shotcrete composite).
  • Spacing: 0.75–1.5 m depending on the ground class.

Pre-support (spiles, forepoling, pipe umbrellas)

In very poor ground (fault zones, soft or loose rock, shallow cover) the ground ahead of the face is supported before excavation:

  • Forepoling / spiling — steel bars or tubes driven ahead of the face in a fan, above the crown.
  • Pipe umbrella (canopy tube) — a series of large steel pipes (76–150 mm) drilled and grouted along the crown ahead of the face, forming a protective umbrella and supported by the ribs.
  • Face reinforcement — fibreglass bolts in the face, and face shotcrete.
  • Ground improvement — pre-grouting, jet grouting or ground freezing ahead of the face.

Support classes

The support is designed as a set of support classes matched to the ground classification (RMR or Q). A typical scheme:

Ground class Rock Excavation Primary support
I (RMR > 80) Very good Full face, long rounds Spot bolts, thin shotcrete on need
II (61–80) Good Full face or heading and bench Systematic bolts, 50–75 mm shotcrete
III (41–60) Fair Heading and bench Bolts, 100 mm fibre shotcrete, lattice girders where needed
IV (21–40) Poor Heading, bench and invert, short rounds 150–200 mm shotcrete, lattice girders/ribs, bolts, forepoling
V (< 21) Very poor Multiple drifts, ring closure, pipe umbrella 250–300 mm shotcrete with ribs, closed invert, face support

The class at each stage is decided by face mapping and monitoring, on the basis of the design classes in the contract.

Rock load (Terzaghi)

Terzaghi's classical approach estimates the vertical rock load on the support of a tunnel with span and height , for descriptive rock classes:

Rock condition Rock load height
Hard and intact 0
Hard, stratified or schistose 0 to 0.5
Massive, moderately jointed 0 to 0.25
Moderately blocky and seamy 0.25 to 0.35
Very blocky and seamy 0.35 to 1.10
Completely crushed but chemically intact 1.10
Squeezing rock up to 2.1 to 4.5

The rock load is on the roof. It was developed for steel ribs and timber; NATM design uses the ground reaction and numerical analysis instead, but Terzaghi's values are still used to check preliminary loads.

Worked ExampleExample — rock load and bolt length

A tunnel of width = 10 m, height = 8 m is in "moderately blocky and seamy" rock with unit weight 26 kN/m³. Taking = 0.30 = 0.30 × 18 = 5.4 m:

on the roof.

The Q-system for the same rock with = 4 and ESR = 1.3 gives a bolt length of m and a bolt spacing of about 1.5 m — the bolts and shotcrete carry the loosened zone, not the whole 5.4 m of rock.

This chapter is in the syllabus of

Open an exam to see where this chapter sits in its syllabus, and to practise it.