Site Organisation & Supervision

Organisation — principles (unity of command, span of control, delegation, scalar chain); types of organisation — line, line and staff, functional (Taylor), committee; Fayol's principles; site organisation of a construction project and duties of site engineers; site layout planning — stores, batching plant, cranes, access roads, temporary facilities; site records and registers — site order book, hindrance register, cement and material registers, daily progress report, test registers; materials and stores management — ABC analysis, EOQ, reorder level, inventory; motivation theories (Maslow, Herzberg, McGregor); communication and meetings — with worked examples.

📑 Contents (10 sections)

Last reviewed 16 Sept 2026 · 8 min read

Organisation and its principles

Organisation is the structure of roles, authority, responsibility and relationships that enables people to work together towards objectives.

Principles of organisation

Principle Meaning
Unity of objective All parts work towards common goals
Unity of command Each person receives orders from one superior only
Span of control Number of subordinates a manager can effectively supervise — narrower for complex work
Scalar chain Clear line of authority from top to bottom
Delegation Authority passed down with responsibility; responsibility cannot be fully delegated
Parity of authority and responsibility Authority should match responsibility
Division of work / specialisation Work divided according to skills
Flexibility and simplicity Structure adapts to changes

Fayol's 14 principles of management

Division of work; authority and responsibility; discipline; unity of command; unity of direction; subordination of individual interest to general interest; remuneration; centralisation; scalar chain; order; equity; stability of tenure; initiative; esprit de corps.

Types of organisation

Type Features Merits Demerits
Line (military/scalar) Direct vertical authority from top to bottom Simple, clear authority, quick decisions, discipline Overloads top managers, no specialists, rigid
Line and staff Line managers command; staff specialists advise (planning, quality, safety, legal) Expert advice with unity of command; suits large projects Line–staff conflicts; staff lacks authority
Functional (Taylor's functional foremanship) Work divided by function; workers receive orders from several functional foremen (e.g. route clerk, instruction card clerk, time and cost clerk, disciplinarian, gang boss, speed boss, repair boss, inspector) Specialisation, efficiency Violates unity of command, confusion, conflicts
Committee Groups of persons for decisions/advice Pooled judgement, coordination Slow, diluted responsibility
Project / matrix See Construction Planning & Project Management Project focus Dual authority (matrix)

Site organisation of a construction project

A typical contractor's site organisation (large project):

  • Project Manager — overall responsibility.
  • Planning and billing engineers, quality control engineer/laboratory, safety officer (staff functions).
  • Construction managers / section in-charges → site engineers → supervisors/foremen → gangs of workers.
  • Stores and purchase, plant and machinery, accounts and administration, human resources.

In government departments (e.g. PWD), the hierarchy commonly runs: Chief Engineer → Superintending Engineer (circle) → Executive Engineer (division) → Assistant Engineer (sub-division) → Junior Engineer (section).

Duties of a site engineer / junior engineer (typical)

  • Setting out works; ensuring work as per drawings and specifications.
  • Supervising labour and contractors; quality control — checking materials and tests.
  • Recording measurements in the MB and maintaining site registers.
  • Preparing progress reports; planning daily/weekly work; material requisitions.
  • Ensuring safety and housekeeping; coordinating with other agencies.
  • Handling hindrances and issuing site instructions (as authorised).

Site layout planning

The site layout shows the location of temporary facilities to ensure efficient, safe and economical operations.

Facilities to be located:

  • Access roads, gates, security, parking.
  • Site office, laboratory, first aid room.
  • Stores — cement godown (raised floor, waterproof, near mixing point), steel yard, aggregate stockpiles, fuel store.
  • Batching plant/mixers — near aggregate stockpiles and cement store, with access for transit mixers.
  • Crane positions — covering the work area and unloading points; hoists.
  • Fabrication yards — reinforcement bending, formwork, precast.
  • Water and power supply, drainage.
  • Labour camps, toilets, canteens (away from hazardous areas).
  • Waste disposal area.

Principles: minimise material handling and travel distances; avoid double handling; keep safe clearances from excavations and overhead lines; separate pedestrian and vehicle routes; allow for changes as work progresses; protect materials from weather and theft.

Site records and registers

Record Purpose
Site order book Instructions to the contractor by the engineer-in-charge, acknowledged by the contractor, with compliance noted
Hindrance register Records hindrances/delays (drawings not issued, site not available, departmental materials delayed) with dates — basis for extension of time
Cement register Daily receipt, issue and balance of cement (especially departmental cement)
Steel and other material registers Receipts, issues and balances
Measurement book Measurements of work done
Daily progress report / site diary Work done, labour and equipment deployed, weather, visitors, problems
Test registers Results of material and concrete tests (cube register, slump)
Labour register / muster roll Attendance and wages
Drawing register Issued drawings and revisions
Equipment log book Working and idle hours, fuel, breakdowns
Safety register / accident register Inspections, incidents

Materials and stores management

Objectives

Ensure the right material, in the right quantity, of the right quality, at the right time and place, at the right price, with minimum inventory cost and no wastage or pilferage.

ABC analysis

Items classified by annual consumption value:

Class Share of items (approx.) Share of value (approx.) Control
A ~10% ~70% Tight control, frequent review
B ~20% ~20% Moderate control
C ~70% ~10% Simple control

Other classifications: VED (vital, essential, desirable — criticality), FSN (fast, slow, non-moving), HML (high, medium, low unit price).

FormulaInventory control

Economic order quantity (EOQ) — minimises the sum of ordering and carrying costs:

= annual demand; = ordering cost per order; = carrying (holding) cost per unit per year. At EOQ, annual ordering cost = annual carrying cost.

Reorder level demand during lead time safety stock Maximum stock reorder level reorder quantity minimum usage during minimum lead time (commonly used formula)