Scheduling and its purposes; bar (Gantt) charts — construction, uses, advantages and limitations; linked bar charts; milestone charts; progress monitoring on bar charts; line of balance for repetitive works; S-curves (cumulative progress and cost); types of schedules — construction, labour, material, equipment and financial schedules; updating and look-ahead schedules — with worked examples.

📑 Contents (10 sections)

Last reviewed 16 Sept 2026 · 5 min read

Scheduling

Scheduling is fixing the start and finish times of each activity on a calendar, respecting logic, durations and resource limits.

Purposes

  • Know when each activity will be done; determine the completion date.
  • Plan procurement of materials, labour and equipment.
  • Coordinate subcontractors and agencies.
  • Provide a baseline for monitoring progress and cash flow.

Bar chart (Gantt chart)

Developed by Henry L. Gantt (early 20th century). Activities are listed vertically and each is shown as a horizontal bar along a time scale; bar length represents duration.

Construction of a bar chart

  1. List the activities (from the WBS).
  2. Estimate durations.
  3. Decide the sequence and start dates.
  4. Draw bars against the time scale; show actual progress by a second bar or shading.
Worked ExampleBar chart for a small building (illustrative)
Activity Duration (weeks) Start week Finish week
Site clearance and setting out 1 1 1
Excavation 2 2 3
Foundation concrete and plinth 3 4 6
Superstructure (RCC frame, masonry) 8 7 14
Plumbing and electrical rough-in 4 11 14
Plastering 3 15 17
Flooring 2 17 18
Painting and finishing 2 19 20

Overall duration: 20 weeks. Plumbing overlaps superstructure (weeks 11–14) — parallel activities are easily visualised.

Advantages

  • Simple to prepare and understand — even by non-technical people.
  • Clear visual picture of time-scale and overlapping activities.
  • Useful for small projects and for presenting summaries.
  • Can show planned vs actual progress and resource loading.

Limitations

  1. Interdependencies between activities are not shown — the effect of delay in one activity on others cannot be seen.
  2. Does not identify critical activities or floats.
  3. Uncertainty in durations cannot be represented.
  4. Difficult to update and to use for large, complex projects with many activities.
  5. Progress in terms of physical percentage is judged subjectively.
  6. No time–cost trade-off analysis.

These limitations led to milestone charts and later network techniques (CPM, PERT).

Linked bar chart

A bar chart with arrows linking dependent activities — shows logic partially; modern software displays Gantt charts linked to network logic.

Milestone chart

A milestone is a significant event (point in time, zero duration) — e.g. "foundation completed", "roof slab cast".

  • A milestone chart is an improvement over a bar chart in which milestones are marked on bars, dividing long activities into sub-activities with key events.
  • Helps monitoring long activities and showing some sequence within an activity.
  • Still does not show interdependencies between milestones of different activities — which led to network diagrams (milestones connected by arrows became the forerunner of PERT networks).

Monitoring progress on bar charts

  • Planned bar vs actual bar drawn beneath or shaded.
  • A status (time-now) line drawn at the reporting date; activities behind the line are behind schedule, ahead are ahead of schedule.
  • Percentage completion marked on bars.

Line of balance (LOB)

A technique for repetitive projects — multi-storey buildings (floor by floor), housing units, pipelines, highways.

  • Plots cumulative units completed (vertical axis) against time (horizontal axis) for each activity/crew — each crew's progress is a line whose slope = production rate.
  • Parallel lines indicate balanced crews moving continuously from unit to unit; converging lines indicate conflicts (crews catching up).
  • Helps maintain continuity of work and identify bottlenecks.