In the TNPSC AE Civil syllabus under Project Management & Estimation · 2 parts
Cost Control & Earned Value Management · Quality Control & Quality Assurance
CIVILGYAN TEST SERIES · civilgyantests.com — free study notes for civil engineering exams
📑 Contents (17 sections)
Part 1 of 2
Cost Control & Earned Value Management
Last reviewed 16 Sept 2026 · 5 min read
Cost control
Cost control ensures that the project is completed within the approved budget by comparing actual costs with planned costs and taking corrective action.
Steps
Prepare a budget (cost baseline) from the estimate, broken down by WBS/cost codes and time.
Record actual costs (labour, materials, equipment, subcontracts, overheads) against cost codes.
Measure work done (progress).
Compare planned, earned and actual costs; compute variances.
Forecast final cost; analyse causes and take corrective actions.
Report to management; update the plan.
Common causes of cost overrun
Inaccurate estimates and incomplete design; scope changes (variations).
Delays — approvals, land acquisition, utility shifting, slow payments, disputes.
Price escalation of materials and wages.
Low productivity, rework and poor quality; equipment breakdown.
Poor site management and wastage; unforeseen ground conditions.
Earned value management (EVM)
EVM integrates scope, schedule and cost to measure performance objectively.
Basic quantities
Term
Also called
Meaning
Planned value (PV)
BCWS — budgeted cost of work scheduled
Budgeted cost of work planned to be completed by the status date
Earned value (EV)
BCWP — budgeted cost of work performed
Budgeted cost of work actually completed by the status date
Estimate at completion (typical — current cost performance continues):
EAC=CPIBAC
Atypical (remaining work at budget rate):EAC=AC+(BAC−EV)Considering both CPI and SPI:EAC=AC+CPI×SPIBAC−EV
Estimate to completeETC=EAC−ACVariance at completionVAC=BAC−EAC
To-complete performance index (to finish within BAC):
TCPI=BAC−ACBAC−EV
(Using EAC in the denominator instead: TCPI=EAC−ACBAC−EV.)
Rough time forecast: estimated duration ≈ planned duration / SPI
Interpretation
CPI
SPI
Status
> 1
> 1
Under budget, ahead of schedule
> 1
< 1
Under budget, behind schedule
< 1
> 1
Over budget, ahead of schedule
< 1
< 1
Over budget, behind schedule
TCPI > 1 — the remaining work must be done more efficiently than planned to meet the budget.
On an S-curve plot, the PV curve is the baseline; if the EV curve is below PV → behind schedule; if AC is above EV → over budget.
Part 2 of 2
Quality Control & Quality Assurance
Last reviewed 16 Sept 2026 · 7 min read
Quality
Quality is conformance to requirements (Crosby) or fitness for use (Juran) — meeting the specified and implied needs of the owner and users.
In construction, quality includes conformance to drawings and specifications, durability, safety, functionality, aesthetics and maintainability.
QC, QA and quality management
Term
Meaning
Quality control (QC)
Operational techniques — inspection, testing, measurement — to verify that products meet requirements; product-oriented, detects defects
Quality assurance (QA)
Planned and systematic activities (procedures, audits, documentation) to provide confidence that quality requirements will be met; process-oriented, prevents defects
Quality management
Overall management function — quality policy, planning, QC, QA and improvement
Total quality management (TQM)
Organisation-wide philosophy of continuous improvement with customer focus and involvement of all employees
ISO 9001 specifies requirements for a quality management system (QMS); the current edition is ISO 9001:2015 (as of the update date of these notes).
Principles include customer focus, leadership, engagement of people, process approach, improvement, evidence-based decision making, relationship management; the 2015 edition emphasises risk-based thinking.
Certification is by accredited third-party bodies.
Quality planning in construction projects
Quality assurance plan (QAP) — scope, organisation and responsibilities, procedures, standards, testing frequencies, documentation.
Inspection and test plan (ITP) — for each activity: what to inspect/test, method, frequency, acceptance criteria, hold points (work cannot proceed until inspected) and witness points.
Method statements, checklists, material approvals (samples, mill certificates), field laboratory, third-party quality audits, non-conformance reports (NCR) and corrective/preventive actions.
Seven basic quality control tools
Check sheet — structured data collection.
Histogram — frequency distribution of data.
Pareto chart — defects ranked by frequency — about 80% of problems from 20% of causes.
Scatter diagram — relationship between two variables.
Control chart — process variation over time.
Stratification (or flow chart in some lists) — separating data by source.
Statistical quality control
Control charts
A control chart plots a quality characteristic over time with a centre line (CL), upper control limit (UCL) and lower control limit (LCL), commonly at ±3σ of the plotted statistic.
Chart
For
Plots
x̄ chart
Variables
Sample means — process average
R chart / s chart
Variables
Sample ranges / standard deviations — dispersion
p chart
Attributes
Fraction defective
np chart
Attributes
Number defective (constant sample size)
c chart
Attributes
Number of defects per unit
∑FormulaControl limits
x̄ chart:UCL=xˉˉ+A2Rˉ, LCL=xˉˉ−A2RˉR chart:UCL=D4Rˉ, LCL=D3Rˉp chart:pˉ±3npˉ(1−pˉ)c chart:cˉ±3cˉ
(Negative LCL is taken as zero.)
Points outside limits or non-random patterns (runs, trends) indicate assignable (special) causes; variation within limits is due to chance (common) causes.
Process capabilityCp=6σUSL−LSL — Cp≥1.33 is commonly regarded as capable.
Acceptance sampling
Deciding to accept or reject a lot based on a sample.
Producer's risk (α) — rejecting a good lot; consumer's risk (β) — accepting a bad lot.
Operating characteristic (OC) curve — probability of acceptance vs lot quality; AQL (acceptable quality level) and LTPD (lot tolerance percent defective).
Cost of quality
Category
Examples
Prevention costs
Training, quality planning, process design
Appraisal costs
Inspection, testing, audits
Internal failure costs
Rework, scrap, repairs before handover
External failure costs
Defects after handover — repairs, claims, reputation loss
Investing in prevention reduces failure costs — the total cost of quality falls.
Six Sigma
Data-driven approach to reduce variation; a Six Sigma process has about 3.4 defects per million opportunities (DPMO) (allowing a 1.5σ shift).
Methodology DMAIC — Define, Measure, Analyse, Improve, Control; roles such as Champions, Black Belts and Green Belts.
Quality control of concrete
∑FormulaTarget mean strength (IS 10262)
fck′=fck+1.65s
s = standard deviation (assumed values are given in IS 10262 when site data are not available); 1.65 corresponds to not more than 5% of results falling below fck.
Sampling frequency (IS 456)
Quantity of concrete in the work (m³)
Number of samples
1–5
1
6–15
2
16–30
3
31–50
4
51 and above
4 + 1 for each additional 50 m³ or part
Each sample consists of three cubes; the sample strength is the average of the three (individual variation limits apply).
Acceptance is judged using the mean of groups of consecutive non-overlapping results and individual results relative to fck, as specified in IS 456 (as amended).
Other site QC for concrete
Tests on materials — cement (setting time, soundness, strength), aggregates (grading, silt, flakiness), water.
Slump test for workability; temperature; air content where required.