Part 1 of 2
Building Estimates — Long Wall-Short Wall & Centre Line Methods
Last reviewed 16 Sept 2026 · 7 min read
Methods of estimating walls
In a building, walls and their foundations have the same cross-section along their length, so quantities are found by multiplying length × cross-sectional dimensions for each layer (excavation, concrete bed, footings, plinth and superstructure). The difficulty lies in corners and junctions, where quantities could be double counted or omitted.
1. Long wall–short wall method
Walls in one direction are treated as long walls and those at right angles as short walls.
- Long wall length (out-to-out) centre-to-centre length one breadth
- Short wall length (in-to-in) centre-to-centre length one breadth
The breadth is the width of that particular layer (trench width, footing width, wall thickness), so the lengths change from layer to layer.
- Quantities for each layer are computed separately for long walls and short walls.
- Simple and less error-prone for rectangular buildings; laborious for buildings with many walls.
2. Centre line method
The total length of the centre lines of all walls is multiplied by the cross-sectional dimensions of each layer.
- At each T-junction (where a cross wall meets a main wall), deduct half the breadth of that layer () from the total centre line length for each junction — because the overlap would otherwise be counted twice.
- At corners (L-junctions), no deduction is needed — the extra length on the outer side balances the shortage on the inner side.
- At a cross (+) junction of walls, deduct one full breadth (two halves).
- Quick and suitable for buildings with walls of uniform section and many junctions (after applying deductions carefully).
3. Partly centre line and partly cross-wall method
Main walls are computed by the centre line method, and cross walls by in-to-in lengths — used where walls have different sections.
Sequence of items in a building estimate
| No. | Item | Unit |
|---|---|---|
| 1 | Earthwork in excavation in foundation trenches | m³ |
| 2 | Lean concrete (e.g. 1 : 4 : 8 PCC) in foundation bed | m³ |
| 3 | Brick/stone masonry in foundation and plinth (footing steps) | m³ |
| 4 | Damp-proof course at plinth level | m² |
| 5 | Filling in plinth (sand/earth) and floor base | m³ |
| 6 | Masonry in superstructure (with deductions for openings, lintels, embedded RCC) | m³ |
| 7 | RCC work — lintels, chajjas, beams, columns, slabs | m³ |
| 8 | Formwork for RCC items | m² |
| 9 | Reinforcement (from BBS) | kg |
| 10 | Flooring — base concrete and floor finish; skirting | m², m³ |
| 11 | Plastering — internal walls, external walls, ceiling | m² |
| 12 | Doors, windows, ventilators — frames and shutters, fittings | m², no. |
| 13 | Roof treatment / waterproofing, parapet, coping | m² |
| 14 | Whitewashing, distempering, painting | m² |
| 15 | Steps, sunshades, rainwater pipes, miscellaneous | as applicable |
| 16 | Water supply, sanitary and electrical installations | lump sum/% |
| 17 | Contingencies, work-charged establishment | % |
Worked estimate — single-room building
Data:
- Internal room size 5.0 m × 4.0 m; walls 300 mm thick in superstructure; height of superstructure (floor to roof slab bottom) 3.0 m.
- Foundation: trench 0.9 m wide, 1.0 m deep below ground level; PCC 1 : 4 : 8 bed 0.9 m wide × 0.2 m thick.
- Brick masonry footings: first step 0.6 m wide × 0.3 m; second step 0.45 m wide × 0.3 m; plinth wall 0.3 m wide × 0.6 m (up to plinth level).
- Openings: one door 1.0 m × 2.1 m; two windows 1.2 m × 1.2 m; RCC lintels 0.3 m wide × 0.15 m deep with 150 mm bearing on each side.
Centre line lengths: long walls c/c m; short walls c/c m Total centre line length (four L-corners, no T-junctions → no deduction)
1. Earthwork in excavation Check by long wall–short wall: long walls out-to-out m (×2 = 12.4 m); short walls in-to-in m (×2 = 6.8 m); total 19.2 m ✓
2. PCC 1 : 4 : 8 in foundation
3. Brick masonry in foundation and plinth
- First step: m³
- Second step: m³
- Plinth wall: m³ Total
4. Damp-proof course (at plinth level) m², less door opening m² → 5.46 m²
5. Brick masonry in superstructure
- Gross: m³
- Deduct door: m³
- Deduct windows: m³
- Deduct lintels: length m → m³ Net
6. RCC lintels
7. RCC roof slab (120 mm thick, resting over walls, no projection)
8. Internal plaster (12 mm) on walls Internal perimeter m → gross m² Door (2.1 m²) and windows (1.44 m² each) are between 0.5 and 3 m² → deduct on one face (taken on the inside face here): m² Net internal plaster
9. External plaster (on superstructure) External perimeter m → (no deductions on this face under the one-face rule for these openings)
10. Ceiling plaster
11. Flooring Floor area (base concrete and finish computed from thicknesses)
The abstract of cost then multiplies each quantity by its rate (from the schedule of rates) and adds contingencies and other provisions.
If an internal cross wall (same foundation section) is added across the room of the example (c/c length 4.3 m), find the centre line length for the excavation layer.
Solution. The cross wall meets the long walls at two T-junctions. For the 0.9 m wide trench, deduct m. Centre line length (a different deduction applies to each layer according to its breadth)