← Estimating, Costing & Valuation

Analysis of Rates

Purpose of rate analysis; factors affecting rates; components — materials (with wastage), labour (task work/output), tools and plant, water charges, overheads and contractor's profit; schedule of rates (CPWD DSR and state SORs) and cost index; material requirements for concrete (dry volume factor), cement mortar and brickwork; labour outputs; step-by-step rate analysis for PCC, brickwork and plastering; market rates, lead and carriage — with solved numericals using explicitly hypothetical rates.

📑 Contents (7 sections)

Last reviewed 16 Sept 2026 · 7 min read

Rate analysis — meaning and purpose

Analysis of rates is the determination of the cost per unit of an item of work (per m³, m², kg etc.) from the quantities of materials and labour required, their current rates, and allowances for tools, plant, overheads and profit.

Purposes

  • Determine a reasonable rate for each item for estimates and tenders.
  • Fix rates for extra/substituted items not in the schedule.
  • Check the reasonableness of contractors' quoted rates.
  • Revise rates when material prices or wages change.
  • Prepare/update the schedule of rates.

Factors affecting rates

  1. Specification and quality of materials and workmanship.
  2. Location of the site — distance (lead) from sources of materials, transport facilities.
  3. Quantity of work (economy of scale).
  4. Labour rates and availability; local wages.
  5. Site conditions — working space, water, weather, height, depth.
  6. Profit, overheads and taxes.
  7. Season and time allowed for completion.

Components of a rate

Component Typical treatment
Materials Quantity per unit of work (including wastage) × rate at site (cost + carriage + loading/unloading + storage)
Labour Number of mason/mazdoor/bhisti days per unit (from output or task work) × daily wage
Tools and plant (T&P), scaffolding Lump sum or small percentage of labour cost, or actual hire charges of machinery
Water charges Commonly about 1% of the cost of materials and labour (or as per departmental rules)
Contractor's profit and overheads Commonly about 10% for profit plus overheads, often combined in schedules as around 15% of the cost (as per the department's analysis)

Percentages vary between departments and years; examinations commonly use water charges 1–1.5% and contractor's profit about 10%.

Schedule of rates and cost index

  • Schedule of rates (SOR) — list of item rates approved by a department for a region and period, e.g. CPWD Delhi Schedule of Rates (DSR) and state PWD SORs, prepared by analysis of rates.
  • Cost index — percentage used to update a base schedule (e.g. DSR) to the current cost level at a particular place and time; Estimated cost = base schedule amount × (1 + cost index %).
  • Market rate items — items not in the schedule, analysed from market rates of materials and labour.

Material requirements

Concrete — dry volume

When dry materials (cement, sand, coarse aggregate) are mixed with water and compacted, the wet volume is less than the sum of the loose dry volumes — voids are filled.

FormulaMaterials for concrete

Dry volume ≈ 1.52–1.57 × wet volume (commonly 1.54 for concrete)

For a nominal mix by volume:

Cement in bags (density of cement ≈ 1440 kg/m³; one bag = 50 kg ≈ 0.0347 m³)

Cement mortar

Dry volume ≈ 1.27–1.33 × wet volume (commonly taken as about 1.3, with some texts adding extra for wastage).

Brickwork

  • Nominal (with mortar) size of a modular brick: 200 × 100 × 100 mm → about 500 bricks per m³ of brickwork.
  • Actual modular brick 190 × 90 × 90 mm → volume of bricks in 1 m³ ≈ m³ → wet mortar ≈ 0.25–0.30 m³ per m³ of brickwork (commonly taken as about 0.25–0.30 m³, with the frog and wastage allowance).
  • With traditional (non-modular) bricks, about 550 per m³ are commonly used in calculations; add wastage for bricks (often 5%).

Plastering

  • Wet mortar = area × thickness; add for filling joints, uneven surfaces and wastage (commonly 20–30%) before converting to dry volume.

Quick check · 5 questions · 3 minutes

Padh liya? Ab dekho kitna yaad raha.

Five exam-level questions from Estimating, Costing & Valuation. No timer, no payment.

Labour — output and task work

  • Task work (outturn) — amount of work one labourer or a gang can do in a day under normal conditions (e.g. m³ of excavation, m² of plaster per mason-day).
  • Labour per unit of work is expressed as mason, beldar/mazdoor, bhisti (water carrier), carpenter, blacksmith days.
  • Output depends on skill, climate, site conditions, height, lead — published departmental analyses give standard figures.

Worked examples (hypothetical rates)

Worked ExampleExample 1 — materials for 1 m³ of PCC 1 : 2 : 4

Solution. Dry volume m³; sum of ratios Cement m³ kg ≈ 6.34 bags Sand 0.44 m³; coarse aggregate 0.88 m³

Worked ExampleExample 2 — rate of 1 m³ of PCC 1 : 2 : 4

Using the quantities of Example 1 and the following hypothetical rates: cement ₹ 400 per bag; sand ₹ 1500 per m³; coarse aggregate ₹ 1800 per m³; labour for 1 m³ — 0.1 mason at ₹ 900/day, 2.0 mazdoor at ₹ 600/day, 0.7 bhisti at ₹ 600/day; T&P ₹ 100; water charges 1% and contractor's profit 10%.

Solution.

  • Cement: 6.34 × 400 = ₹ 2536
  • Sand: 0.44 × 1500 = ₹ 660
  • Coarse aggregate: 0.88 × 1800 = ₹ 1584
  • Labour: 0.1 × 900 + 2.0 × 600 + 0.7 × 600 = 90 + 1200 + 420 = ₹ 1710
  • T&P: ₹ 100

Total = ₹ 6590 Water charges 1% = ₹ 65.90 → ₹ 6655.90 Contractor's profit 10% = ₹ 665.59 → Rate ≈ ₹ 7321.49 per m³

Worked ExampleExample 3 — materials for 1 m³ of brickwork in CM 1 : 6

Use modular bricks (500 per m³ with 5% wastage) and wet mortar 0.30 m³ per m³ of brickwork, dry volume factor 1.30.

Solution. Bricks 525 Dry mortar m³ Cement m³ kg ≈ 1.60 bags; sand 0.334 m³

Worked ExampleExample 4 — 12 mm plaster in CM 1 : 4 over 100 m²

Add 30% for joints, unevenness and wastage; dry volume factor 1.27.

Solution. Wet mortar m³ → with 30% extra m³ → dry m³ Cement m³ kg ≈ 11.4 bags; sand 1.585 m³

Worked ExampleExample 5 — updating with a cost index

An estimate prepared on the base schedule comes to ₹ 50 lakh. The cost index for the place is 28% (hypothetical). Find the estimated cost.

Solution. 50 × 1.28 = ₹ 64 lakh

Frequently tested points

  • Rate = materials + labour + T&P + water charges (1%) + contractor's profit (10%) and overheads.
  • Rate analysis used for estimates, tenders, extra items, checking quoted rates and preparing SORs (e.g. CPWD DSR); cost index updates schedules.
  • Dry volume of concrete ≈ 1.54 × wet; mortar ≈ 1.27–1.33 × wet.
  • Cement density ≈ 1440 kg/m³; 1 bag = 50 kg ≈ 0.0347 m³.
  • 1 m³ PCC 1 : 2 : 4 needs ≈ 6.3–6.4 bags cement, 0.44 m³ sand, 0.88 m³ aggregate; 1 : 1.5 : 3 ≈ 8.2 bags.
  • Modular bricks ≈ 500 per m³; mortar ≈ 0.25–0.30 m³ per m³ brickwork.
  • Labour expressed as mason/mazdoor/bhisti days from task work (outturn).
Common MistakeCommon mistakes
  • Using wet volume directly to find material quantities (forgetting the dry volume factor).
  • Computing profit before adding water charges and other components (follow the order specified in the question).
  • Treating illustrative rates as current market rates.
Revision SummaryChapter summary
  1. Rate analysis finds the unit cost of each item from material and labour requirements and current prices.
  2. Rates include materials with wastage, labour, tools and plant, water charges, overheads and profit.
  3. Schedules of rates and cost indices standardise and update rates for departments and regions.
  4. Dry volume factors convert wet concrete and mortar volumes into cement, sand and aggregate quantities.
  5. Worked analyses for concrete, brickwork and plaster show the complete procedure.

Practise this chapter for your exam

This chapter is in the syllabus of 27 exams. Take its chapter test, then the full mock tests of your exam.

🎯 Finished reading? Test yourself

Rate Analysis & Specifications — free chapter test

Exam-style questions from the syllabus chapter “Rate Analysis & Specifications”, with solutions after you submit. Free — you can start without an account.

Take the free test →

✅ Free — no sign-up needed

How ready are you for Estimating, Costing & Valuation?

Ten questions from the real syllabus, about five minutes. You will see your score and which subject is holding you back — before you create any account.

10 questions · no timer · no payment