← Estimating, Costing & Valuation

Bill of Quantities, Abstract of Cost & Schedules of Rates

What a Bill of Quantities (BOQ) is and how it is prepared from measured quantities; the abstract of estimated cost with contingencies, work-charged establishment and other percentage charges; the schedules of rates (CPWD DSR, state SSR/SOR) with cost-index and area-weightage adjustments; and a worked example of a BOQ and an abstract of cost with explicitly hypothetical rates.

📑 Contents (5 sections)

Last reviewed 30 Sept 2026 · 9 min read

Bill of Quantities (BOQ)

A Bill of Quantities is a document that lists the items of work to be carried out in a contract, each with a brief description, unit and quantity. In a tender, the contractor writes a rate and the amount against each item; the total forms the tender price. After award, the BOQ is the basis of the contract payment (in an item-rate contract) and for measuring variations.

Purposes

  • Gives all bidders the same quantities to price, so the tenders are directly comparable.
  • Forms the basis of the estimate (with rates from the schedule of rates), and later of the contract price.
  • Used for interim payments (measured quantity × contract rate) and for valuing variations.
  • Helps planning, procurement and cash-flow forecasting.

How a BOQ is prepared

FormulaSteps in preparing a BOQ
  1. Study the drawings, specifications and site conditions.
  2. Divide the work into sections in the order of construction (earthwork, foundation, superstructure, finishes, services) or by trades.
  3. Take off the quantities of each item from the drawings, using the standard methods of measurement (IS 1200 in India, or the CPWD specifications).
  4. Enter the item description in a standard form, with the specification reference, so that the rate covers all the work described.
  5. Abstract (squaring and summarising) the quantities item by item, converting the dimensions to the unit of measurement (cum, sqm, rm, kg, no.).
  6. Add provisional sums, prime cost (PC) sums and provisional quantities where the details are not known.
  7. Check the totals, the units and the descriptions, then issue the BOQ with the tender.

Format of a BOQ

Item No. Description of item Unit Quantity Rate (₹) Amount (₹)
1 Earthwork in excavation in foundation in ordinary soil up to 1.5 m depth cum
2 Plain cement concrete 1:4:8 in foundation cum
3 Reinforced cement concrete M25 in columns, beams and slabs cum
4 Reinforcement steel Fe 500 kg
5 Brickwork in superstructure, cement mortar 1:6 cum

The rate and amount columns are left blank for the bidder in a tender BOQ, and are filled by the estimator in an estimate.

Good practice

  • One item = one clearly defined work (with the specification); avoid vague descriptions.
  • Use the units and the mode of measurement of IS 1200 so that there is no dispute.
  • Separate materials supplied by the client (with the recovery rate) from the contractor's.
  • Group lump-sum items (mobilisation, testing, insurance) separately.
  • Provisional sums for work whose scope is not yet defined; PC sums for specialist items purchased through nominated suppliers.
  • Types of contract — item-rate (measured against the BOQ; the type most used), lump sum (a fixed price — the BOQ is for information), percentage rate (bidders quote a percentage above or below the estimate rates), and unit-price.

Abstract of estimated cost

The abstract of cost is a summary sheet that lists each main head or item with its quantity, rate and amount, and adds the percentage charges, giving the total estimated cost. It is the top sheet of the estimate submitted for administrative approval and technical sanction.

Items in the abstract

Head Explanation
Cost of the works items (from the BOQ) Sum of quantity × rate for each item
Contingencies An allowance for unforeseen expenditure — usually 3–5 % of the estimated cost (the actual percentage is set by the department's rules)
Work-charged establishment Cost of the temporary staff (supervisors, chowkidars, mates) engaged on the work and paid from the work cost; about 1–2 % or as decided
Tools and plant (T & P) Allowance for special tools and equipment: about 1 % where required
Quality control and testing Percentage or lump sum for the tests of materials and works
Water supply and electric connection charges, sanitary and electrical installations Often estimated separately, as a percentage of the building cost (e.g., electrical 7.5–15 %, plumbing 5–10 %, depending on the type) or in detail
Escalation and cost-index adjustments Where the work runs over a long period
Centage charges (departmental/supervision charges) Percentage for the department's administration and supervision (sometimes 5–15 % in older systems)
Taxes (GST) and labour cess As per the rules (for example, the cess on construction workers' welfare is 1 % of the cost of construction)
Land, consultancy, and other charges For a complete project estimate
Total (grand) cost Rounded to an appropriate figure

The percentages differ between organisations and state rules; the values above are indicative — always use the applicable departmental order.

Estimate approval process (typical)

  1. Preliminary estimate (for the administrative approval).
  2. Detailed estimate and abstract prepared from the drawings.
  3. Technical sanction by the competent engineer (the authority depends on the amount).
  4. Administrative approval by the government (allocating the funds).
  5. Tender, award and agreement; revised estimates if the cost is likely to exceed the sanctioned amount by more than the permitted limit (typically 5–10 %).

Quick check · 5 questions · 3 minutes

Padh liya? Ab dekho kitna yaad raha.

Five exam-level questions from Estimating, Costing & Valuation. No timer, no payment.

Schedules of Rates (SOR)

A Schedule of Rates is a published list of standard rates for the items of work, compiled by a department for use in estimating and in valuing changes. It gives the analysed rate for each item (including materials, labour, plant, overheads and profit) at the base location and date.

Main schedules in India

  • CPWD Delhi Schedule of Rates (DSR) — the base for CPWD works; issued every few years and kept current between editions by a cost index (use the latest edition in force), with the rate analysis (Analysis of Rates, AoR) published separately; rates apply to Delhi and are adjusted for other cities by the CPWD cost index ("cost index of the city" over Delhi).
  • State Schedules of Rates (SSR/SOR) — issued by the state PWD or the water resources departments (yearly or every 2–3 years), with regional or district-wise rates for materials and labour.
  • Railway (RSOR), MES, NHAI, and other departmental schedules, and Basic Schedule of Rates (BSR) for standard materials.

Use and adjustment

  • Base rate + cost index — the rate is updated to the current date with the published cost index (a percentage increase over the base): e.g., DSR rate × .
  • Area weightage (location factor) — a percentage above or below the schedule for a given place, to allow for local materials and labour.
  • Lead and lift — extra for the carriage of materials beyond the standard lead and for the height (lift) beyond the schedule limits.
  • Non-schedule (NS) items — items not in the schedule are priced by rate analysis at the market rates, with the approval of the competent authority.
  • Market-rate justification — recorded for the items where the market is different from the schedule.
  • Escalation — for long contracts, a formula (with indices of material, labour and fuel) adjusts the payment.

Worked example — BOQ and abstract of cost

The rates below are hypothetical figures for illustration only, not schedule values.

BOQ for a small RCC culvert (extract)

No. Item Unit Qty Rate (₹) Amount (₹)
1 Excavation in ordinary soil cum 120 250 30,000
2 PCC 1:4:8 bed cum 15 5,500 82,500
3 RCC M25 in slab and walls cum 60 9,000 540,000
4 Reinforcement Fe 500 kg 7,200 75 540,000
5 Shuttering sqm 300 600 180,000
6 Backfilling and compaction cum 90 300 27,000
Total of items ₹ 1,399,500

Abstract of cost

Head Amount (₹)
Cost of items 13,99,500
Contingencies @ 3 % 41,985
Work-charged establishment @ 1.5 % 20,993
Quality control @ 0.5 % 6,998
Sub-total 14,69,476
GST/other taxes @ 18 % (applied on the works portion as per rules) 2,64,506
Total estimated cost 17,33,982

Rounded, the estimated cost = ₹ 17.34 lakh.

Worked ExampleExample — updating a schedule rate

A DSR base rate for brickwork is ₹ 6,500 per cum. The cost index for the city is 12 % above the base, and the area weightage is 4 %.

Updated rate = 6,500 × (1 + 0.12) = ₹ 7,280; with area weightage, ₹ 7,280 × 1.04 = ₹ 7,571 per cum.

(Whether the area weightage is applied to the base or the indexed rate depends on the departmental order; state the assumption in the estimate.)

Frequently tested points

  • BOQ: list of items with description, unit and quantity; the bidder fills in the rates; the basis of tender comparison, payment and variations.
  • IS 1200 defines the mode of measurement for items; the units are cum, sqm, rm, kg, nos.
  • Abstract of cost: items total + contingencies (3–5 %) + work-charged establishment + other charges = the total estimated cost.
  • Schedule of Rates: published standard rates (CPWD DSR, state SOR); updated with the cost index; area weightage and lead/lift adjust the rate.
  • Non-schedule (NS) items are priced by rate analysis at market rates.
  • Item-rate contract is measured against the BOQ; lump-sum contract has a fixed price.
  • Technical sanction (by the engineer) precedes the administrative approval and the tender in some systems (order depends on the department).
Common MistakeCommon mistakes
  • Writing a vague item description that leaves the scope open to dispute.
  • Adding contingencies twice (in the rate and in the abstract).
  • Using an old schedule of rates without the cost-index update.
Revision SummaryChapter summary
  1. A BOQ lists the items, units and quantities so that tenders are comparable and payments are measured.
  2. It is prepared by dividing the work, taking off quantities per IS 1200, and abstracting them by item.
  3. The abstract of cost adds contingencies, establishment, taxes and other charges to the item total.
  4. Schedules of rates (DSR, state SOR) give standard rates, updated by cost index and area weightage.
  5. Non-schedule items are priced by rate analysis at market rates.

Practise this chapter for your exam

This chapter is in the syllabus of 6 exams. Take its chapter test, then the full mock tests of your exam.

🎯 Finished reading? Test yourself

Bill of Quantities & Abstract of Cost — free chapter test

Exam-style questions from the syllabus chapter “Bill of Quantities & Abstract of Cost”, with solutions after you submit. Free — you can start without an account.

Take the free test →

✅ Free — no sign-up needed

How ready are you for Estimating, Costing & Valuation?

Ten questions from the real syllabus, about five minutes. You will see your score and which subject is holding you back — before you create any account.

10 questions · no timer · no payment