← Construction Planning & Management

Cost Control & Earned Value Management

Project cost control — budgeting, cost codes, monitoring and corrective action; causes of cost overrun; earned value management (EVM) — planned value, earned value and actual cost; cost and schedule variances; cost and schedule performance indices; estimate at completion, estimate to complete, variance at completion and to-complete performance index; interpretation of S-curves; cash flow control — with a fully worked earned value problem.

📑 Contents (5 sections)

Last reviewed 16 Sept 2026 · 5 min read

Cost control

Cost control ensures that the project is completed within the approved budget by comparing actual costs with planned costs and taking corrective action.

Steps

  1. Prepare a budget (cost baseline) from the estimate, broken down by WBS/cost codes and time.
  2. Record actual costs (labour, materials, equipment, subcontracts, overheads) against cost codes.
  3. Measure work done (progress).
  4. Compare planned, earned and actual costs; compute variances.
  5. Forecast final cost; analyse causes and take corrective actions.
  6. Report to management; update the plan.

Common causes of cost overrun

  • Inaccurate estimates and incomplete design; scope changes (variations).
  • Delays — approvals, land acquisition, utility shifting, slow payments, disputes.
  • Price escalation of materials and wages.
  • Low productivity, rework and poor quality; equipment breakdown.
  • Poor site management and wastage; unforeseen ground conditions.

Earned value management (EVM)

EVM integrates scope, schedule and cost to measure performance objectively.

Basic quantities

Term Also called Meaning
Planned value (PV) BCWS — budgeted cost of work scheduled Budgeted cost of work planned to be completed by the status date
Earned value (EV) BCWP — budgeted cost of work performed Budgeted cost of work actually completed by the status date
Actual cost (AC) ACWP — actual cost of work performed Actual cost incurred for the work completed
Budget at completion (BAC) — Total budget of the project
FormulaVariances and indices

Cost variance (negative → over budget) Schedule variance (negative → behind schedule)

Cost performance index ( → over budget) Schedule performance index ( → behind schedule)

FormulaForecasts

Estimate at completion (typical — current cost performance continues):

Atypical (remaining work at budget rate): Considering both CPI and SPI:

Estimate to complete Variance at completion

To-complete performance index (to finish within BAC):

(Using EAC in the denominator instead: .)

Rough time forecast: estimated duration ≈ planned duration / SPI

Interpretation

CPI SPI Status
> 1 > 1 Under budget, ahead of schedule
> 1 < 1 Under budget, behind schedule
< 1 > 1 Over budget, ahead of schedule
< 1 < 1 Over budget, behind schedule
  • TCPI > 1 — the remaining work must be done more efficiently than planned to meet the budget.
  • On an S-curve plot, the PV curve is the baseline; if the EV curve is below PV → behind schedule; if AC is above EV → over budget.

This chapter is in the syllabus of

Open an exam to see where this chapter sits in its syllabus, and to practise it.