Last reviewed 16 Sept 2026 · 5 min read
Cost control
Cost control ensures that the project is completed within the approved budget by comparing actual costs with planned costs and taking corrective action.
Steps
- Prepare a budget (cost baseline) from the estimate, broken down by WBS/cost codes and time.
- Record actual costs (labour, materials, equipment, subcontracts, overheads) against cost codes.
- Measure work done (progress).
- Compare planned, earned and actual costs; compute variances.
- Forecast final cost; analyse causes and take corrective actions.
- Report to management; update the plan.
Common causes of cost overrun
- Inaccurate estimates and incomplete design; scope changes (variations).
- Delays — approvals, land acquisition, utility shifting, slow payments, disputes.
- Price escalation of materials and wages.
- Low productivity, rework and poor quality; equipment breakdown.
- Poor site management and wastage; unforeseen ground conditions.
Earned value management (EVM)
EVM integrates scope, schedule and cost to measure performance objectively.
Basic quantities
| Term | Also called | Meaning |
|---|---|---|
| Planned value (PV) | BCWS — budgeted cost of work scheduled | Budgeted cost of work planned to be completed by the status date |
| Earned value (EV) | BCWP — budgeted cost of work performed | Budgeted cost of work actually completed by the status date |
| Actual cost (AC) | ACWP — actual cost of work performed | Actual cost incurred for the work completed |
| Budget at completion (BAC) | — | Total budget of the project |
Cost variance (negative → over budget) Schedule variance (negative → behind schedule)
Cost performance index ( → over budget) Schedule performance index ( → behind schedule)
Estimate at completion (typical — current cost performance continues):
Atypical (remaining work at budget rate): Considering both CPI and SPI:
Estimate to complete Variance at completion
To-complete performance index (to finish within BAC):
(Using EAC in the denominator instead: .)
Rough time forecast: estimated duration ≈ planned duration / SPI
Interpretation
| CPI | SPI | Status |
|---|---|---|
| > 1 | > 1 | Under budget, ahead of schedule |
| > 1 | < 1 | Under budget, behind schedule |
| < 1 | > 1 | Over budget, ahead of schedule |
| < 1 | < 1 | Over budget, behind schedule |
- TCPI > 1 — the remaining work must be done more efficiently than planned to meet the budget.
- On an S-curve plot, the PV curve is the baseline; if the EV curve is below PV → behind schedule; if AC is above EV → over budget.