← Construction Planning & Management

Contracts, Tendering & Arbitration

Contract essentials under the Indian Contract Act, 1872 — valid, void and voidable contracts; types of construction contracts — lump sum, item rate (unit rate), percentage rate, cost plus (percentage, fixed fee, target cost), labour, turnkey/EPC, design-build; PPP models — BOT, BOOT, BOO, DBFOT, HAM, annuity; FIDIC forms; tendering process — NIT, tender documents, pre-bid meeting, EMD, two-bid system, e-tendering, evaluation (L1, QCBS), negotiation and award; important contract conditions — performance security, advances, price variation, extension of time, liquidated damages, defect liability, variations, termination; claims and dispute resolution — negotiation, mediation, conciliation, dispute boards, arbitration under the Arbitration and Conciliation Act, 1996, litigation.

📑 Contents (8 sections)

Last reviewed 16 Sept 2026 · 8 min read

A contract is an agreement enforceable by law (Indian Contract Act, 1872).

Essentials of a valid contract

  1. Offer (proposal) and acceptance.
  2. Lawful consideration.
  3. Competent parties — of the age of majority, sound mind, not disqualified by law.
  4. Free consent — not caused by coercion, undue influence, fraud, misrepresentation or mistake.
  5. Lawful object.
  6. Not expressly declared void; certainty and possibility of performance.
Term Meaning
Valid contract Satisfies all essentials — enforceable
Void contract Not enforceable by law (e.g. unlawful object, or becomes impossible)
Voidable contract Enforceable at the option of one party (e.g. consent obtained by coercion or fraud)
Void agreement Never enforceable from the start

Types of construction contracts

Type Features Suitability / risk
Lump sum contract Contractor quotes a fixed total price for the complete work per drawings and specifications Well-defined designs; contractor bears quantity risk; variations difficult to value
Item rate (unit rate / schedule) contract Contractor quotes rates for each item in the bill of quantities; payment = measured quantity × rate Most common in public works; owner bears quantity risk; flexible for quantity changes
Percentage rate contract Contractor quotes a percentage above/below the departmental schedule of rates estimate Simple evaluation; common in PWD works
Cost plus percentage Actual cost + a percentage of cost as fee Urgent/undefined works; no incentive to economise — cost rises with fee
Cost plus fixed fee Actual cost + fixed fee Some incentive to finish early; owner bears cost risk
Cost plus fluctuating fee / target cost Fee varies with performance against a target cost (savings/overruns shared) Encourages economy
Labour contract Contractor supplies labour only; owner supplies materials Small works; owner controls materials
Piece work Payment per unit of work for small jobs without formal agreement Petty works
Turnkey / EPC contract Single contractor responsible for engineering, procurement and construction, handing over a ready-to-use facility, usually at a lump sum price Owner transfers design and construction risk; single-point responsibility
Design-build Same entity designs and constructs Faster (overlapping design and construction)
Negotiated contract Terms settled by negotiation with one or a few contractors Specialised/urgent works

Public–private partnership (PPP) models

Model Meaning
BOT (Build–Operate–Transfer) Private party builds, operates (collects tolls/user charges) for a concession period, then transfers to government
BOOT (Build–Own–Operate–Transfer) Private party also owns the asset during concession, then transfers
BOO (Build–Own–Operate) Ownership stays with the private party (no transfer)
DBFOT (Design–Build–Finance–Operate–Transfer) Private party designs and finances as well
BOT (Annuity) Government pays fixed annuities to the concessionaire; traffic risk with government
HAM (Hybrid Annuity Model) Used for national highways in India — government pays part of the project cost (commonly 40%) during construction; balance by the developer, recovered through annuity payments with interest; toll/revenue risk with government
EPC Not PPP — government finances; contractor builds for a fixed price

FIDIC forms of contract

Published by the International Federation of Consulting Engineers (FIDIC):

  • Red Book — construction works designed by the employer.
  • Yellow Book — plant and design-build (contractor designs).
  • Silver Book — EPC/turnkey projects.
  • Green Book — short form for smaller/simple works.
  • White Book — client–consultant agreement.

Tendering process

  1. Preparation of tender documents — notice inviting tender (NIT), instructions to bidders, conditions of contract, specifications, drawings, bill of quantities, forms of bid and security.
  2. Notice inviting tender (NIT) — published on e-procurement portals/newspapers: name and estimated cost of work, time of completion, earnest money deposit (EMD), eligibility, dates of sale/submission/opening.
  3. Pre-qualification (for large works) — financial capacity, experience, equipment, personnel.
  4. Pre-bid meeting — clarification of queries; corrigenda/addenda.
  5. Submission — usually e-tendering; single-bid or two-bid system (technical bid + financial bid in separate envelopes/folders).
  6. Opening — technical bids first; financial bids of technically qualified bidders only.
  7. Evaluation — arithmetic checks, responsiveness; lowest evaluated responsive bidder (L1) for works; QCBS (quality and cost based selection) for consultancy.
  8. Negotiation (only as permitted by rules), letter of acceptance/award, performance security, signing of agreement, return of EMD to unsuccessful bidders.
  • Earnest money deposit (EMD) / bid security — ensures bidders do not withdraw or refuse to sign; forfeited if the bidder backs out. The amount is fixed by the department's rules (usually a small percentage of estimated cost, or bid security declaration).
  • Unbalanced bid (front loading) — high rates for early items and low for later ones.
  • Single tender, limited tender, open tender, global tender — depending on value and urgency.
  • Cartelisation and collusive bidding — prohibited practices.

Important conditions of contract

Condition Purpose
Performance security (guarantee) Ensures due performance; forfeited on default — a percentage of contract value as per rules
Security deposit / retention money Deducted from running bills; released after defect liability period
Mobilisation advance Interest-bearing or interest-free advance to start work, against bank guarantee, recovered from bills
Secured advance Against materials brought to site
Price variation (escalation) clause Adjusts payment for changes in prices of materials, labour and fuel using indices
Extension of time (EOT) For delays not attributable to the contractor
Liquidated damages (LD) / compensation for delay Pre-estimated damages for delay by the contractor, usually subject to a maximum percentage
Defect liability period (DLP) Period after completion during which the contractor must rectify defects
Variations / extra and substituted items Changes in quantity or scope, with rules for rates (deviation limits)
Termination / foreclosure Rights to terminate for default or convenience
Force majeure Relief for events beyond control
Dispute resolution clause Procedure for settling disputes (e.g. dispute board, arbitration)

Claims and dispute resolution

Common causes of disputes: delays, variations, unclear specifications, quantity differences, payment delays, escalation, unforeseen site conditions, termination.

Method Features
Negotiation Parties settle directly — cheapest, fastest
Mediation Neutral mediator facilitates settlement; non-binding unless agreed
Conciliation Conciliator may propose terms; a settlement agreement signed by parties is binding (Part III of the 1996 Act)
Dispute Adjudication/Review Board (DAB/DRB) Experts appointed during the project give decisions/recommendations quickly
Arbitration Private adjudication by arbitrator(s); award is binding and enforceable like a court decree, with limited grounds of challenge
Litigation Courts — slow and costly

Arbitration and Conciliation Act, 1996 (key points)

  • Based on the UNCITRAL Model Law; amended notably in 2015, 2019 and 2021.
  • An arbitration agreement must be in writing (clause in the contract or separate agreement).
  • Parties may choose the number of arbitrators, but it must not be an even number; failing agreement, a sole arbitrator.
  • Arbitrators must be independent and impartial (disclosure requirements introduced in 2015).
  • Time limit for award (after 2015 amendment, Section 29A): generally 12 months from completion of pleadings, extendable by 6 months by consent of parties; further extension only by the court.
  • Fast track procedure (Section 29B) — award on written pleadings, generally within 6 months, if parties agree.
  • An award can be set aside by a court only on limited grounds (Section 34) — e.g. incapacity, invalid agreement, lack of proper notice, matters beyond the submission, improper composition, conflict with public policy.
  • Interim measures by the court (Section 9) or the tribunal (Section 17).

Frequently tested points

  • Valid contract essentials: offer and acceptance, consideration, competent parties, free consent, lawful object.
  • Void (unenforceable) vs voidable (at the option of one party).
  • Lump sum (fixed price, contractor bears quantity risk); item rate (BOQ rates, most common in PWD); percentage rate (above/below SOR); cost plus (owner bears cost risk; cost plus percentage gives no incentive to economise).
  • Turnkey/EPC = single-point responsibility for design, procurement, construction.
  • BOT, BOOT, BOO, DBFOT; HAM — government pays about 40% during construction, annuities later.
  • FIDIC: Red (employer design), Yellow (design-build), Silver (EPC), Green (short form).
  • Tender: NIT → pre-bid → submission (two-bid) → technical then financial opening → L1 → award → performance security → agreement.
  • EMD — bid security; performance security — contract performance; retention released after DLP.
  • LD — pre-estimated damages for delay; EOT for excusable delays; price variation clause for inflation.
  • Arbitration Act 1996 (UNCITRAL); odd number of arbitrators; award within 12 (+6) months; Section 34 challenge; Section 29B fast track.
Common MistakeCommon mistakes
  • Confusing EMD (bid security) with performance security.
  • Calling EPC a PPP model.
  • Treating mediation outcomes as binding without a signed settlement.
Revision SummaryChapter summary
  1. Construction contracts must meet the essentials of the Indian Contract Act, 1872.
  2. Lump sum, item rate, percentage rate, cost plus, labour, EPC/turnkey and design-build contracts allocate risk differently.
  3. PPP models such as BOT, BOOT, BOO, DBFOT and HAM involve private finance and operation; FIDIC forms provide international standard conditions.
  4. Tendering proceeds from NIT and bid documents through two-bid evaluation to award, with EMD and performance security.
  5. Key conditions govern advances, escalation, time extension, damages and defects, while disputes are resolved by negotiation, mediation, conciliation, dispute boards, arbitration or litigation.

Practise this chapter for your exam

This chapter is in the syllabus of 24 exams. Take its chapter test, then the full mock tests of your exam.

🎯 Finished reading? Test yourself

Contracts & Legal Aspects — free chapter test

Exam-style questions from the syllabus chapter “Contracts & Legal Aspects”, with solutions after you submit. Free — you can start without an account.

Take the free test →