← Bridge Engineering

Bridge Construction Methods — Launching & Erection

How bridges are actually built — falsework and staging, precast girder launching by cranes and launching trusses, cast-in-situ balanced cantilever, precast segmental span-by-span erection, incremental launching, push-launching of steel girders, floating and lifting methods, and the temporary works and safety checks that go with them.

📑 Contents (10 sections)

Last reviewed 30 Sept 2026 · 6 min read

Why the method matters

The way a bridge is built decides its stresses during construction, its cost, its speed and the impact on traffic or water below. The method is chosen at the design stage and the structure is designed for it: a girder designed for a launching sequence needs different reinforcement or prestress than the same girder cast on falsework.

Cast-in-situ on falsework

The girder or slab is cast in place on staging (falsework) supported from the ground.

  • Advantages: no heavy plant, flexible geometry, monolithic behaviour.
  • Limits: needs firm ground below; blocks traffic or water; slow; the formwork must be adequate against settlement of the staging.
  • Care: design of the staging for the wet-concrete load with safety factors, camber for deflection, sequence of pour to control cracking, and striking only when concrete reaches the required strength.
  • Suits short viaducts, flyovers over low ground, and skew or curved decks.

Precast girder launching

Girders are made in a casting yard and brought to the site.

Method Description Suitable for
Crane erection Mobile or crawler cranes lift each girder onto the piers Short girders up to about 40 m; accessible ground
Twin cranes / gantry Two cranes lift together Heavier girders
Launching truss / gantry A truss spans between piers and moves forward on rails; trolleys lower the girder Viaducts; long girders; rivers or heavy traffic below
Beam launcher Lighter launching frame moving over piers Highway and metro girders
Barge / floating crane Girders carried by barge and lifted Wide rivers and sea crossings

Before launching the girder is checked for lifting stresses (pick-up points), stability against lateral tilting during lifting and on the launcher (the top flange in compression can buckle laterally), and bearing seating. Lateral stability during transport and placement is often the governing check for slender I-girders.

Balanced cantilever construction

The bridge is built outward from the pier in both directions at the same time, so the moments on either side balance.

  • Cast-in-situ: a form traveller (moving formwork) casts segments 3–5 m long; each segment is prestressed to the previous one after the concrete has gained strength.
  • Precast segments: segments are cast in a yard (match-cast against each other so they fit) and lifted into position by a lifting frame, crane or launching gantry; they are glued with epoxy and prestressed.
  • Stability: the cantilever is stabilised by a temporary pier table fixed to the pier or by props; unbalanced load (one segment more than the other, or a crane) is checked.
  • Closure: the two cantilevers meet at mid-span; a closing segment is cast with the cantilevers locked together (with temporary struts) to avoid movement while concrete hardens. Continuity tendons are then stressed.
  • Use: spans 60–250 m for PSC box girders; also cable-stayed and extradosed bridges.

This chapter is in the syllabus of

Open an exam to see where this chapter sits in its syllabus, and to practise it.