← Quantitative Aptitude

Time & Work, Pipes & Cisterns

Work as a rate — one day's work, adding rates, and the LCM (total units) method; efficiency and its inverse relation with time; the men–days–hours formula; working together, leaving partway, joining partway and working on alternate days; wages shared in the ratio of work done; pipes and cisterns as the same problem with emptying pipes as negative rates, leaks, and a pipe closed before the tank is full — with fully worked examples.

📑 Contents (7 sections)

Last reviewed 22 Sept 2026 · 6 min read

Work as a rate

If a person finishes a job in days, then in one day they do of it. Rates add:

For two people, .

The LCM method

Instead of fractions, call the whole job the LCM of the given days. Each person's rate is then a whole number of units a day, and the arithmetic stays clean.

For A in 12 days and B in 18 days: total work units; A does 3 units/day, B does 2, together 5 → days. Most exam problems are fastest this way.

Efficiency

FormulaEfficiency and time
  • Efficiency : if A is twice as efficient as B, A takes half the time.
  • If A is times as efficient as B and together they take days, then A alone takes and B alone .
  • Percent more efficient: "A is 25% more efficient than B" means rates are , so times are .

The men–days–hours relation

FormulaWork equation

men working hours a day for days complete work . Drop when hours are not mentioned and drop when the job is the same in both cases. Men and days are inversely proportional; men and work are directly proportional.

Working together in the usual patterns

  • Someone leaves partway: compute the work done together up to that day, then divide the remainder by the rate of whoever is left.
  • Someone joins partway: the same, in reverse.
  • Alternate days: add the two rates as a repeating two-day block and count how many whole blocks fit; finish the remainder with whoever's turn it is.
  • Wages: the money is shared in the ratio of work done, which for the same period is the ratio of efficiencies.

Pipes and cisterns

The same arithmetic with a sign: a filling pipe is a positive rate, an emptying pipe or a leak is negative.

FormulaCistern rules
  • Filling pipes and hours, waste pipe hours:
  • Full in hours without a leak, hours with it (): the leak alone empties a full tank in hours
  • A pipe closed early: let it run hours, write (work by pipe 1) + (work by pipe 2) , and solve for
  • A negative net rate means the tank never fills

Worked examples

Worked ExampleExample 1 — working together

A can do a job in 12 days and B in 18 days. How long together?

Solution. 7.2 days (LCM method: 36 units, 3 + 2 = 5 a day).

Worked ExampleExample 2 — one rate from the pair

A and B together finish a job in 8 days; A alone takes 12 days. How long does B take alone?

Solution. → 24 days.

Worked ExampleExample 3 — efficiency

A is twice as efficient as B, and together they finish in 12 days. Find their separate times.

Solution. Let B's rate be , A's ; . B alone 36 days, A alone 18 days.

Worked ExampleExample 4 — men and days

Ten men finish a job in 15 days. How long will 6 men take?

Solution. 25 days.

Worked ExampleExample 5 — men, days and hours

Eight men working 6 hours a day finish a job in 10 days. How many days will 12 men working 5 hours a day take?

Solution. 8 days.

Worked ExampleExample 6 — leaving partway

A alone takes 20 days and B alone 30 days. They work together for 5 days, then A leaves. How long does B take to finish?

Solution. In 5 days together: . Remaining at B's rate → 17.5 days.

Worked ExampleExample 7 — alternate days

A can do a job in 10 days, B in 15. They work on alternate days, A starting. When is it finished?

Solution. A two-day block does . Six blocks complete the job, so it takes 12 days.

Worked ExampleExample 8 — wages

A and B finish a job together in 6 days; A alone would take 10. They are paid ₹ 3,000 in all. Find each share.

Solution. B's rate , so the rates are . A gets ₹ 1,800, B ₹ 1,200.

Worked ExampleExample 9 — pipes with a waste pipe

Pipe A fills a tank in 6 hours, pipe B in 8 hours, and pipe C empties it in 12 hours. All three are opened together.

Solution. → 4.8 hours.

Worked ExampleExample 10 — a leak

A cistern fills in 4 hours, but with a leak it takes 5 hours. How long would the leak alone take to empty a full cistern?

Solution. → 20 hours (formula: ).

Worked ExampleExample 11 — a pipe closed early

Two pipes fill a tank in 20 and 30 minutes. Both are opened, but the second is closed after some time and the tank fills in 18 minutes. When was it closed?

Solution. 3 minutes.

Quick check · 5 questions · 3 minutes

Padh liya? Ab dekho kitna yaad raha.

Five exam-level questions from Quantitative Aptitude. No timer, no payment.

Practise this chapter for your exam

This chapter is in the syllabus of 20 exams. Take its chapter test, then the full mock tests of your exam.

✅ Free — no sign-up needed

How ready are you for Quantitative Aptitude?

Ten questions from the real syllabus, about five minutes. You will see your score and which subject is holding you back — before you create any account.

10 questions · no timer · no payment