Last reviewed 22 Sept 2026 · 6 min read
Work as a rate
If a person finishes a job in days, then in one day they do of it. Rates add:
For two people, .
The LCM method
Instead of fractions, call the whole job the LCM of the given days. Each person's rate is then a whole number of units a day, and the arithmetic stays clean.
For A in 12 days and B in 18 days: total work units; A does 3 units/day, B does 2, together 5 → days. Most exam problems are fastest this way.
Efficiency
- Efficiency : if A is twice as efficient as B, A takes half the time.
- If A is times as efficient as B and together they take days, then A alone takes and B alone .
- Percent more efficient: "A is 25% more efficient than B" means rates are , so times are .
The men–days–hours relation
men working hours a day for days complete work . Drop when hours are not mentioned and drop when the job is the same in both cases. Men and days are inversely proportional; men and work are directly proportional.
Working together in the usual patterns
- Someone leaves partway: compute the work done together up to that day, then divide the remainder by the rate of whoever is left.
- Someone joins partway: the same, in reverse.
- Alternate days: add the two rates as a repeating two-day block and count how many whole blocks fit; finish the remainder with whoever's turn it is.
- Wages: the money is shared in the ratio of work done, which for the same period is the ratio of efficiencies.
Pipes and cisterns
The same arithmetic with a sign: a filling pipe is a positive rate, an emptying pipe or a leak is negative.
- Filling pipes and hours, waste pipe hours:
- Full in hours without a leak, hours with it (): the leak alone empties a full tank in hours
- A pipe closed early: let it run hours, write (work by pipe 1) + (work by pipe 2) , and solve for
- A negative net rate means the tank never fills
Worked examples
A can do a job in 12 days and B in 18 days. How long together?
Solution. 7.2 days (LCM method: 36 units, 3 + 2 = 5 a day).
A and B together finish a job in 8 days; A alone takes 12 days. How long does B take alone?
Solution. → 24 days.
A is twice as efficient as B, and together they finish in 12 days. Find their separate times.
Solution. Let B's rate be , A's ; . B alone 36 days, A alone 18 days.
Ten men finish a job in 15 days. How long will 6 men take?
Solution. 25 days.
Eight men working 6 hours a day finish a job in 10 days. How many days will 12 men working 5 hours a day take?
Solution. 8 days.
A alone takes 20 days and B alone 30 days. They work together for 5 days, then A leaves. How long does B take to finish?
Solution. In 5 days together: . Remaining at B's rate → 17.5 days.
A can do a job in 10 days, B in 15. They work on alternate days, A starting. When is it finished?
Solution. A two-day block does . Six blocks complete the job, so it takes 12 days.
A and B finish a job together in 6 days; A alone would take 10. They are paid ₹ 3,000 in all. Find each share.
Solution. B's rate , so the rates are . A gets ₹ 1,800, B ₹ 1,200.
Pipe A fills a tank in 6 hours, pipe B in 8 hours, and pipe C empties it in 12 hours. All three are opened together.
Solution. → 4.8 hours.
A cistern fills in 4 hours, but with a leak it takes 5 hours. How long would the leak alone take to empty a full cistern?
Solution. → 20 hours (formula: ).
Two pipes fill a tank in 20 and 30 minutes. Both are opened, but the second is closed after some time and the tank fills in 18 minutes. When was it closed?
Solution. 3 minutes.