← Building Materials · NCRTC Supervisor Civil

Chapter 25 of 25

Construction Techniques

In the NCRTC Supervisor Civil syllabus under Building Materials · 2 parts

📑 Contents (17 sections)

Part 1 of 2

Construction Practices — Setting Out, Excavation, Shoring & Underpinning

Last reviewed 16 Sept 2026 · 9 min read

Site preparation and setting out

  1. Site investigation — soil exploration, water table, existing services, access.
  2. Site clearance — removal of vegetation, debris and topsoil; demolition of old structures.
  3. Levelling and grading; provision of temporary drainage, access roads, stores, water and power.
  4. Temporary benchmark (TBM) established near the site.
  5. Setting out of foundations — baseline from the site plan; centre lines of walls or column grids set out with tape, theodolite or total station; right angles by 3-4-5 method; diagonals checked; profile boards fixed outside the excavation to preserve lines; trench widths marked with lime/chalk powder (see Setting Out of Works).

Excavation

Methods and equipment

  • Manual excavation — pickaxes, spades, crowbars, baskets — small works, restricted spaces, near services.
  • Mechanical excavation:
Equipment Use
Hydraulic excavator (backhoe) Trenches and pits below machine level, loading trucks
Face shovel Excavating above track level (cuts, quarries)
Dragline Large, loose or wet excavations below level, long reach
Clamshell Deep, confined vertical excavations (wells, shafts)
Bulldozer Pushing and spreading earth, clearing, short-haul
Scraper Excavating, hauling and spreading over medium distances
Loader (front-end/wheel loader) Loading loose material
Grader Fine levelling and shaping
Trenchers Narrow continuous trenches for pipes and cables
  • Excavation in rock — rock breakers (hydraulic hammers), controlled blasting, chemical expansive agents where blasting is not permitted.

Stability of excavation sides

Trench sides may collapse because of soil weight, water, vibration, surcharge from spoil and equipment. Protection by:

  • Sloping the sides to a safe angle (depending on soil) or benching (steps).
  • Timbering (shoring of trenches) or proprietary trench boxes and hydraulic shoring.
  • Keeping spoil and equipment away from the edge.
  • Dewatering where the water table is high.

Excavations deeper than about 1.5 m generally require protective measures and safe access (ladders), barricading and lighting.

Timbering of trenches

System Soil condition Arrangement
Stay bracing Firm soil, moderate depth Vertical sheeting planks (poling boards) placed opposite each other at intervals and held apart by horizontal struts
Box sheeting Loose soil, moderate depth Vertical sheeting boards placed close together, held by horizontal walings and struts — forming a box
Vertical sheeting Deep trenches in soft soil Box sheeting installed in stages (with offsets/steps as depth increases)
Runner system Very loose soils (running sand) Long vertical runners (thick planks with pointed ends) driven ahead of excavation, supported by walings and struts
Sheet piling Very soft/waterlogged soils, deep and wide excavations Steel (or timber/concrete) sheet piles driven before excavation, interlocking to resist earth and water pressure, supported by walings and struts or anchors

Components: sheeting/poling boards (vertical planks against soil), walings/wales (horizontal members), struts (horizontal compression members across the trench), wedges, puncheons (short vertical props between walings).

Dewatering (control of groundwater)

Method Description / suitability
Open sump pumping Water collected in sumps and pumped out — shallow excavations, cohesive or coarse soils with modest inflow
Well point system Closely spaced small-diameter wells (well points) connected to a header pipe and vacuum pump — lowers water table in sands and gravels, a few metres per stage (multi-stage for deeper lowering)
Deep well system Large-diameter wells with submersible pumps around the excavation — deep lowering in permeable soils
Electro-osmosis Electric current drives water towards cathode wells — silts and fine soils of low permeability
Grouting Cement, clay or chemical grouts injected to reduce permeability (and strengthen)
Freezing Ground frozen by circulating refrigerants — very difficult waterlogged ground (temporary)
Cut-off walls Sheet piles, diaphragm walls, secant piles to exclude water

Shoring

Shoring is the construction of temporary supports to structures (walls, buildings) that are unsafe or require support during repairs, alterations, adjacent excavation or underpinning.

Type Arrangement Use
Raking (inclined) shores Inclined members (rakers) with their upper ends against a wall plate fixed to the wall (with needles and cleats), and lower ends on a sole plate bedded on the ground; bracing between rakers Support walls that tend to bulge or lean outward; common for walls of damaged or adjacent buildings. Rakers are commonly inclined at about 60–70° to the horizontal (not flatter than about 45° or steeper than about 75°)
Flying (horizontal) shores Horizontal struts spanning between two parallel walls, with wall plates, needles and inclined struts (straining pieces) When an intermediate building is demolished and rebuilt between two existing buildings
Dead (vertical) shores Horizontal needles passed through holes in the wall and supported on vertical props on both sides, with sole plates Support the upper part of a wall while its lower portion or foundation is removed/rebuilt, or openings are made

Underpinning

Underpinning is the process of strengthening, deepening or extending the foundations of an existing structure.

Purposes

  • Foundations have settled or are inadequate (weak soil, deterioration).
  • Deeper excavation adjacent to the building (new basement or foundations nearby).
  • Increased loads (additional storeys, change of use).
  • Creating a basement below an existing building.
  • Repairing damage from subsidence, tree roots or leaking drains.

Methods

Method Description
Pit (mass concrete) method The wall is supported (by needles and dead shores if needed); short sections (pits) of foundation are excavated below the existing footing and filled with new foundation concrete, working in alternate bays so that the wall is never unsupported over a long length
Pile method Piles installed along both sides of the wall; needles or pile caps (beams) pass through the wall to transfer loads to the piles
Cantilever needle and pile method Piles on one side only (where access is restricted), with cantilevered needle beams
Mini-piles / micro-piles Small-diameter bored and grouted piles drilled through or alongside existing foundations — minimal disturbance, restricted access
Jack piling Precast pile segments jacked down using the weight of the structure as reaction
Grouting and ground improvement Cement, chemical or jet grouting to strengthen soil below foundations
Beam and base / raft underpinning New reinforced concrete beams or rafts transferring loads to new bases

Precautions: survey and monitor the building (cracks, levels); provide shoring; work in short sections; avoid undermining; ensure new foundations are well bonded (dry pack/grout between old and new).

Demolition

  • Planning: structural survey, disconnection of services, safety and environmental measures (dust, noise), permits.
  • Methods: manual (top-down, element by element), mechanical (excavators with breakers, crushers, wrecking balls, high-reach machines), controlled implosion (explosives — tall structures in open surroundings), diamond wire and wall sawing (precise cutting).
  • Sequence: generally reverse of construction — non-structural elements first, then roof and floors from top downward.
  • Waste management: segregation and recycling of concrete, steel, bricks, timber (construction and demolition waste rules).

Construction equipment

Category Equipment
Earthmoving Excavators, shovels, draglines, clamshells, bulldozers, scrapers, loaders, graders, dumpers/tippers
Compaction Smooth-wheeled, sheep-foot, pneumatic-tyred and vibratory rollers, plate compactors, rammers
Hoisting Tower cranes, mobile cranes, crawler cranes, derricks, hoists, winches, gantry cranes
Concrete equipment Batching and mixing plants, drum mixers, transit mixers, concrete pumps (boom and line), vibrators, power trowels
Piling equipment Pile drivers (drop hammers, diesel and hydraulic hammers, vibratory hammers), rotary piling rigs
Pavement equipment Hot mix plants, pavers, slip-form pavers, bitumen distributors
Tunnelling Tunnel boring machines, drill jumbos, muck loaders
FormulaOutput of an excavator (approximate)

= bucket capacity (m³); = bucket fill factor; = job efficiency factor (e.g. working minutes per hour ÷ 60); = cycle time (seconds).

Part 2 of 2

Scaffolding & Formwork

Last reviewed 16 Sept 2026 · 11 min read

Scaffolding

Scaffolding is a temporary structure erected to provide working platforms for workers and materials at heights during construction, repair, painting and maintenance.

Components

Component Description
Standards Vertical members (poles/tubes) supporting the scaffold, placed on base plates/sole plates
Ledgers Horizontal members running parallel to the wall, connecting standards
Putlogs Transverse horizontal members resting on ledgers at one end and inserted into holes (putlog holes) in the wall at the other
Transoms Transverse members resting on ledgers of both rows of standards (in independent/double scaffolds)
Braces Diagonal members fixed across standards for stiffness and stability
Boards (working platform) Timber or steel planks laid on putlogs/transoms
Guard rails and toe boards Edge protection against falls of persons and materials
Base plates / sole plates Spread load of standards on the ground
Couplers (clamps) Right-angle, swivel, putlog and sleeve couplers joining steel tubes
Ties Connect the scaffold to the building for stability
Bridle Member bridging a window/door opening to support putlogs
Rakers Inclined supports

Types of scaffolding

Type Description Use
Single (bricklayer's / putlog) scaffold One row of standards parallel to the wall (commonly about 1.2 m away); putlogs rest on ledgers and in holes in the wall Brick masonry construction
Double (mason's / independent) scaffold Two rows of standards, one near the wall and one away; transoms span between ledgers — no support from the wall Stone masonry (holes in stone walls are difficult), independent support
Cantilever (needle) scaffold Standards supported on needles projecting through openings from inside the building When the ground is not suitable or free for standards (traffic, busy streets), upper parts of tall buildings
Suspended (swinging) scaffold Working platform suspended by ropes/chains from the roof and raised or lowered by winches Painting, cleaning, repairs, glazing of tall buildings
Trestle scaffold Platform on movable trestles or ladders Interior work at small heights (painting, plastering ceilings)
Steel tubular scaffold Steel tubes and couplers Quick erection, strong, fire resistant, reusable — modern construction
System scaffolds (cuplock, ringlock) Prefabricated standards with node connections for ledgers Rapid assembly, formwork support, industrial work
Bamboo scaffold Bamboo poles lashed with coir ropes Traditional, economical in India and Asia; requires careful inspection
Mobile tower scaffold Wheeled aluminium/steel tower with locking castors Light maintenance and services work
Patented scaffolds Proprietary brackets and frames Special applications

Safety of scaffolds

  • Erected, altered and dismantled by trained persons and inspected before use and after bad weather.
  • Firm base — base plates and sole plates on compacted ground; no loose bricks as supports.
  • Adequate bracing and ties to the structure.
  • Working platforms fully boarded, of adequate width, with guard rails (commonly about 1 m high), intermediate rails and toe boards.
  • Safe access by ladders or stair towers; ladders secured and extending above platforms.
  • Do not overload platforms; keep materials evenly distributed.
  • Use safety harnesses where edge protection is incomplete; keep clear of overhead power lines.

Formwork (shuttering)

Formwork is the temporary (or permanent) mould into which fresh concrete is placed and in which it is supported until it gains enough strength to support itself. The term centering is used for supports of slabs, beams and arches, and shuttering for vertical faces.

Requirements of good formwork

  1. Strong — to carry the weight of wet concrete, reinforcement, workers, equipment and impact loads.
  2. Rigid — minimal deflection so that concrete members retain their shape and dimensions.
  3. Watertight joints — to prevent leakage of cement slurry (which causes honeycombing).
  4. Smooth inner surface for the desired finish; release agents to prevent adhesion.
  5. Accurate in shape, size, line and level.
  6. Easy to erect and strip without damaging the concrete; allow removal of sides before soffits.
  7. Reusable many times; light but durable.
  8. Economical — formwork is a significant part of the cost of RCC work.
  9. Supported on a firm base with adequate bracing against lateral forces.

Materials

Material Features
Timber (planks, battens, joists) Easy to cut and fix, light; limited reuse, absorbs water, warps
Plywood (shuttering / film-faced ply) Large smooth panels, good finish, more reuses than planks
Steel (panels, props, spans) Strong, rigid, many reuses, smooth finish; heavy, costly initially, needs release agents and care against rust
Aluminium Light, many reuses — system formwork for repetitive housing
Plastic / FRP Light, many reuses, special shapes (waffle moulds, column forms)
Fabric and cardboard (sonotubes) Circular columns, special shapes
Permanent (stay-in-place) formwork Profiled steel decking, precast planks, EPS insulated concrete forms

Components

Sheathing (surface in contact with concrete), joists/battens and ledgers/runners (support sheathing), props (posts) — adjustable steel props or timber posts — bracing, wedges (levelling and easy stripping), ties (through-bolts, snap ties for wall forms), spacers, yokes/column clamps, head trees, sole plates, form release agents (mould oil).

Formwork for different members

Member Arrangement
Foundations/footings Side boards held by stakes and cleats; for pedestals, box forms
Columns Four side panels held by yokes or column clamps, spaced closer near the bottom (higher concrete pressure); cleaning/inspection opening at the base; plumb and braced
Beams Bottom (soffit) board on head trees supported by props, and side boards held by cleats and struts; sides removed earlier than soffit
Slabs Decking (plywood/steel panels) on joists and ledgers supported by props, braced
Walls Panels on both faces held apart by spacers and tied with through-ties, braced with walers and push–pull props
Stairs Inclined soffit decking with riser boards and side boards (stringers)

Special formwork systems

System Description / use
Slip form Formwork raised continuously by jacks while concrete is placed (no joints) — chimneys, silos, cooling towers, lift cores, bridge piers
Jump (climbing) form Formwork lifted in stages (jumps) after each lift of concrete gains strength — high-rise cores, tall piers
Table (flying) form Large pre-assembled slab formwork tables moved by crane from floor to floor — repetitive slab construction
Tunnel form Room-sized steel forms casting walls and slabs together — mass housing, hotels
Aluminium panel systems (monolithic construction) Light aluminium wall and slab panels for rapid cycle times — mass housing
Waffle / ribbed slab moulds Plastic or FRP pans forming ribbed slabs
Travelling forms Tunnel linings, culverts, bridge decks (form travellers for balanced cantilevers)
Permanent formwork Composite steel decks, precast planks, ICF — remain part of the structure

Finished reading? Test yourself.

A timed chapter test from the NCRTC Supervisor Civil series, on exactly this chapter.

Practice this chapter →