Analysis of Rates

Last reviewed 16 Sept 2026 · 7 min read

Rate analysis — meaning and purpose

Analysis of rates is the determination of the cost per unit of an item of work (per m³, m², kg etc.) from the quantities of materials and labour required, their current rates, and allowances for tools, plant, overheads and profit.

Purposes

  • Determine a reasonable rate for each item for estimates and tenders.
  • Fix rates for extra/substituted items not in the schedule.
  • Check the reasonableness of contractors' quoted rates.
  • Revise rates when material prices or wages change.
  • Prepare/update the schedule of rates.

Factors affecting rates

  1. Specification and quality of materials and workmanship.
  2. Location of the site — distance (lead) from sources of materials, transport facilities.
  3. Quantity of work (economy of scale).
  4. Labour rates and availability; local wages.
  5. Site conditions — working space, water, weather, height, depth.
  6. Profit, overheads and taxes.
  7. Season and time allowed for completion.

Components of a rate

Component Typical treatment
Materials Quantity per unit of work (including wastage) × rate at site (cost + carriage + loading/unloading + storage)
Labour Number of mason/mazdoor/bhisti days per unit (from output or task work) × daily wage
Tools and plant (T&P), scaffolding Lump sum or small percentage of labour cost, or actual hire charges of machinery
Water charges Commonly about 1% of the cost of materials and labour (or as per departmental rules)
Contractor's profit and overheads Commonly about 10% for profit plus overheads, often combined in schedules as around 15% of the cost (as per the department's analysis)

Percentages vary between departments and years; examinations commonly use water charges 1–1.5% and contractor's profit about 10%.

Schedule of rates and cost index

  • Schedule of rates (SOR) — list of item rates approved by a department for a region and period, e.g. CPWD Delhi Schedule of Rates (DSR) and state PWD SORs, prepared by analysis of rates.
  • Cost index — percentage used to update a base schedule (e.g. DSR) to the current cost level at a particular place and time; Estimated cost = base schedule amount × (1 + cost index %).
  • Market rate items — items not in the schedule, analysed from market rates of materials and labour.

Material requirements

Concrete — dry volume

When dry materials (cement, sand, coarse aggregate) are mixed with water and compacted, the wet volume is less than the sum of the loose dry volumes — voids are filled.

FormulaMaterials for concrete

Dry volume ≈ 1.52–1.57 × wet volume (commonly 1.54 for concrete)

For a nominal mix by volume:

Cement in bags (density of cement ≈ 1440 kg/m³; one bag = 50 kg ≈ 0.0347 m³)

Cement mortar

Dry volume ≈ 1.27–1.33 × wet volume (commonly taken as about 1.3, with some texts adding extra for wastage).

Brickwork

  • Nominal (with mortar) size of a modular brick: 200 × 100 × 100 mm → about 500 bricks per m³ of brickwork.
  • Actual modular brick 190 × 90 × 90 mm → volume of bricks in 1 m³ ≈ m³ → wet mortar ≈ 0.25–0.30 m³ per m³ of brickwork (commonly taken as about 0.25–0.30 m³, with the frog and wastage allowance).
  • With traditional (non-modular) bricks, about 550 per m³ are commonly used in calculations; add wastage for bricks (often 5%).

Plastering

  • Wet mortar = area × thickness; add for filling joints, uneven surfaces and wastage (commonly 20–30%) before converting to dry volume.

Labour — output and task work

  • Task work (outturn) — amount of work one labourer or a gang can do in a day under normal conditions (e.g. m³ of excavation, m² of plaster per mason-day).
  • Labour per unit of work is expressed as mason, beldar/mazdoor, bhisti (water carrier), carpenter, blacksmith days.
  • Output depends on skill, climate, site conditions, height, lead — published departmental analyses give standard figures.

Worked examples (hypothetical rates)

Worked ExampleExample 1 — materials for 1 m³ of PCC 1 : 2 : 4

Solution. Dry volume m³; sum of ratios Cement m³ kg ≈ 6.34 bags Sand 0.44 m³; coarse aggregate 0.88 m³

Worked ExampleExample 2 — rate of 1 m³ of PCC 1 : 2 : 4

Using the quantities of Example 1 and the following hypothetical rates: cement ₹ 400 per bag; sand ₹ 1500 per m³; coarse aggregate ₹ 1800 per m³; labour for 1 m³ — 0.1 mason at ₹ 900/day, 2.0 mazdoor at ₹ 600/day, 0.7 bhisti at ₹ 600/day; T&P ₹ 100; water charges 1% and contractor's profit 10%.

Solution.

  • Cement: 6.34 × 400 = ₹ 2536
  • Sand: 0.44 × 1500 = ₹ 660
  • Coarse aggregate: 0.88 × 1800 = ₹ 1584
  • Labour: 0.1 × 900 + 2.0 × 600 + 0.7 × 600 = 90 + 1200 + 420 = ₹ 1710
  • T&P: ₹ 100

Total = ₹ 6590 Water charges 1% = ₹ 65.90 → ₹ 6655.90 Contractor's profit 10% = ₹ 665.59 → Rate ≈ ₹ 7321.49 per m³

Worked ExampleExample 3 — materials for 1 m³ of brickwork in CM 1 : 6

Use modular bricks (500 per m³ with 5% wastage) and wet mortar 0.30 m³ per m³ of brickwork, dry volume factor 1.30.

Solution. Bricks 525 Dry mortar m³ Cement m³ kg ≈ 1.60 bags; sand 0.334 m³

Worked ExampleExample 4 — 12 mm plaster in CM 1 : 4 over 100 m²

Add 30% for joints, unevenness and wastage; dry volume factor 1.27.

Solution. Wet mortar m³ → with 30% extra m³ → dry m³ Cement m³ kg ≈ 11.4 bags; sand 1.585 m³

Worked ExampleExample 5 — updating with a cost index

An estimate prepared on the base schedule comes to ₹ 50 lakh. The cost index for the place is 28% (hypothetical). Find the estimated cost.

Solution. 50 × 1.28 = ₹ 64 lakh

Frequently tested points

  • Rate = materials + labour + T&P + water charges (1%) + contractor's profit (10%) and overheads.
  • Rate analysis used for estimates, tenders, extra items, checking quoted rates and preparing SORs (e.g. CPWD DSR); cost index updates schedules.
  • Dry volume of concrete ≈ 1.54 × wet; mortar ≈ 1.27–1.33 × wet.
  • Cement density ≈ 1440 kg/m³; 1 bag = 50 kg ≈ 0.0347 m³.
  • 1 m³ PCC 1 : 2 : 4 needs ≈ 6.3–6.4 bags cement, 0.44 m³ sand, 0.88 m³ aggregate; 1 : 1.5 : 3 ≈ 8.2 bags.
  • Modular bricks ≈ 500 per m³; mortar ≈ 0.25–0.30 m³ per m³ brickwork.
  • Labour expressed as mason/mazdoor/bhisti days from task work (outturn).
Common MistakeCommon mistakes
  • Using wet volume directly to find material quantities (forgetting the dry volume factor).
  • Computing profit before adding water charges and other components (follow the order specified in the question).
  • Treating illustrative rates as current market rates.
Revision SummaryChapter summary
  1. Rate analysis finds the unit cost of each item from material and labour requirements and current prices.
  2. Rates include materials with wastage, labour, tools and plant, water charges, overheads and profit.
  3. Schedules of rates and cost indices standardise and update rates for departments and regions.
  4. Dry volume factors convert wet concrete and mortar volumes into cement, sand and aggregate quantities.
  5. Worked analyses for concrete, brickwork and plaster show the complete procedure.

Part 2 of 2

Specifications

Last reviewed 16 Sept 2026 · 7 min read

Meaning and purpose

Specifications are written descriptions of the quality of materials, workmanship, method of construction, tests and mode of measurement for each item of work. Drawings show what is to be built (shape, size, location); specifications describe how and with what quality.

Purposes

  1. Define the quality of materials and workmanship precisely.
  2. Provide the basis for rate analysis and estimating.
  3. Enable uniform tendering — all contractors quote for the same work.
  4. Guide the execution and supervision of work at site.
  5. Serve as a legal document (part of the contract) for settling disputes.
  6. Allow checking of work and materials through specified tests.

Types of specifications

Type Description
General (brief/outline) specifications Short description of the class of building and main features — type of foundation, walls, roof, flooring, finishing — used with preliminary estimates
Detailed specifications Complete description of each item — materials, proportions, method of preparation and execution, curing, tests, finishing, mode of measurement and payment — used with detailed estimates and contracts
Standard specifications Published by organisations and used as references — e.g. CPWD Specifications, MoRTH Specifications for Road and Bridge Works, state PWD specifications, relevant BIS standards
Manufacturer's specifications Instructions from manufacturers for proprietary products (waterproofing compounds, adhesives, sealants)
Open specifications Allow materials/products meeting stated requirements from any source — encourages competition
Closed (proprietary/restricted) specifications Specify a particular brand/product — used where required, but restrict competition (public works generally require "or equivalent")
Performance specifications Specify required results/performance (e.g. strength, durability, compaction density) — method left to the contractor
Prescriptive (method) specifications Specify materials and methods in detail (e.g. mix proportions, number of roller passes)

Principles of writing specifications

  1. Clear, concise and unambiguous language; avoid vague terms ("good quality", "as directed" without limits).
  2. Consistent with drawings and other contract documents; any conflict to be resolved by stated precedence.
  3. Follow a logical sequence — materials → preparation → execution → curing/protection → tests → measurement → rate.
  4. Quote standard specifications and BIS codes instead of repeating long details where appropriate.
  5. Specify tests and acceptance criteria.
  6. Avoid repetition and contradictory clauses.
  7. Be fair to both owner and contractor; realistic requirements.
  8. Use the imperative/future tense ("shall").

Detailed specifications of common items (outline)

Earthwork in excavation for foundations

  • Site cleared; centre lines and trench widths marked from drawings; excavation to lines and levels.
  • Bottom of trench levelled, rammed and watered; soft or loose pockets removed and filled with concrete or as directed.
  • Excavated earth deposited at a specified distance from the edge of the trench; shoring/timbering and dewatering where necessary.
  • Measurement in m³ as trench dimensions; rate includes lead and lift as specified.

Plain cement concrete (e.g. 1 : 4 : 8 in foundations)

  • Materials: OPC/PPC as specified; clean, well-graded sand and hard broken stone aggregate of specified size.
  • Mixing: in a mechanical mixer (hand mixing on a watertight platform where permitted), specified water–cement ratio.
  • Placing and compaction: in layers not exceeding a specified thickness; compacted by rammers/vibrators; no segregation.
  • Curing: kept wet for the specified period (commonly at least 7 days for OPC, longer for blended cements).
  • Measurement: m³; no deduction for small embedded items.

Reinforced cement concrete

  • Formwork rigid, watertight, true to line; reinforcement as per drawings and BBS, with specified cover blocks, laps and binding.
  • Design mix concrete; slump and cube tests; placing within the initial setting time; vibration; construction joints at specified locations.
  • Curing for the specified period; stripping of formwork after specified periods.
  • Measurement in m³ (concrete), m² (formwork) and kg (steel), as specified in the item.

First-class brickwork in cement mortar

  • Bricks: first-class, well burnt, of uniform size and colour, with metallic ringing sound, free from cracks; soaked in water before use.
  • Mortar: cement and sand in specified proportions, used within the specified time (e.g. before initial setting).
  • Laying: in English bond (unless specified), frog upwards, joints fully filled, joint thickness not exceeding about 10 mm; courses truly horizontal and walls plumb; not more than a specified height (commonly about 1 m) raised in a day.
  • Curing: kept wet for about 7–10 days; joints raked for plastering/pointing.
  • Measurement: m³.

Damp-proof course

  • Typically cement concrete (e.g. 1 : 1.5 : 3), 40–50 mm thick with or without waterproofing compound, or bitumen coats as specified, over the full width of the wall at plinth level; not provided across door openings unless specified; cured.

Cement plastering

  • Joints raked, surface cleaned and wetted; dots and screeds for uniform thickness.
  • Mortar of specified proportions; applied in one or two coats as specified (e.g. 12 mm internal, 15–20 mm external in two coats).
  • Finished with a wooden float/trowel; curing for about 7 days.
  • Measurement in m² with IS 1200 deductions.

Flooring (cement concrete / tiles)

  • Base concrete over compacted filling; floor laid in panels with dividing strips; specified slopes; curing; polishing/grinding for terrazzo; skirting as specified.

Whitewashing, colour washing and painting

  • Surface cleaned, holes filled, priming where required.
  • Lime wash/colour wash in specified number of coats, each coat allowed to dry.
  • Paints (distemper, emulsion, enamel) applied as per manufacturer's instructions, with specified coats.
  • Measurement in m² (with coefficients for doors, windows and grilles).

General specifications of buildings (classes)

Many textbooks classify buildings for general specifications as:

Class Typical features
First-class building First-class brick masonry in cement mortar, RCC roof, high-quality flooring (terrazzo/marble/tiles), best teak wood doors and windows, full internal services
Second-class building Masonry in cement or lime mortar, RCC roof, cement concrete/tile flooring, good quality wood, standard services
Third-class building Second-class bricks, lime or mud mortar, sloping sheet/tile roof or RB roof, simple flooring, local wood
Fourth-class building Kutcha construction — sun-dried bricks or mud walls, thatch or sheet roof, earthen floors

(Detailed descriptions vary between textbooks; the classification is a teaching convention rather than a code requirement.)

Specifications in contract documents

  • Contract documents typically include: agreement, notice inviting tender, conditions of contract, specifications, drawings, schedule of quantities (bill of quantities) and rates, and correspondence/addenda.
  • The contract states the order of precedence if documents conflict (e.g. specific over general, figured dimensions over scaled).

Frequently tested points

  • Drawings show "what"; specifications describe quality of materials, workmanship, method, tests and measurement ("how").
  • General (brief) specifications → preliminary estimate; detailed specifications → detailed estimate and contract.
  • Standard specifications: CPWD Specifications, MoRTH (roads and bridges), BIS standards.
  • Open (any source), closed/proprietary (particular brand), performance (results), prescriptive (method).
  • Writing principles: clear, concise, consistent with drawings, logical sequence, cite standards, "shall".
  • Brickwork (typical): soaked bricks, frog up, joints ≤ about 10 mm, about 1 m height per day, English bond, curing about 7–10 days.
  • Specifications form part of the contract and help settle disputes.
Common MistakeCommon mistakes
  • Writing vague specifications ("best quality", "as directed") that cannot be enforced.
  • Conflicts between drawings and specifications without a precedence clause.
  • Using proprietary specifications in public works without allowing equivalents.
Revision SummaryChapter summary
  1. Specifications describe materials, workmanship, methods, tests and measurement; drawings show geometry.
  2. General specifications support preliminary estimates; detailed specifications support detailed estimates and contracts.
  3. Standard, manufacturer's, open, closed, performance and prescriptive specifications serve different needs.
  4. Good specifications are clear, consistent, logical and refer to standards.
  5. Detailed specifications of earthwork, concrete, masonry, DPC, plaster, flooring and finishes follow a set sequence, and specifications are a key contract document.