← Irrigation Engineering · GSSSB Work Assistant Civil

Chapter 7 of 12

Water Conveyance, Storage & Distribution

In the GSSSB Work Assistant Civil syllabus under Irrigation Engineering · 2 parts

📑 Contents (12 sections)

Part 1 of 2

Canal Irrigation & Design of Alluvial Canals

Last reviewed 16 Sept 2026 · 8 min read

Canal systems

A canal is an artificial channel that carries water from a river or reservoir to the fields.

Classification

Basis Types
Function Irrigation canal; power canal; feeder canal (feeds two or more canals); carrier canal (carries water for another canal and also irrigates); navigation canal
Hierarchy (discharge) Main canal (usually no direct irrigation) → branch canals → major distributaries → minor distributaries → watercourses (field channels, maintained by farmers)
Alignment Ridge (watershed) canal; contour canal; side-slope canal
Source / supply Perennial canal; inundation canal
Soil Alluvial canal; non-alluvial canal
Lining Lined; unlined
Financial output Productive (expected to earn a return); protective (constructed mainly to protect against famine)

Canal alignment

Alignment Description Features
Ridge (watershed) canal Runs along the ridge (watershed) line of the area Irrigates both sides; no cross-drainage works needed (drainages flow away from the ridge); main canals in plains follow this where possible
Contour canal Follows a contour, with a small bed slope Irrigates one side only; crosses natural drainages — needs cross-drainage works; common in hilly areas
Side-slope canal Aligned roughly perpendicular to contours (parallel to natural drainage) No cross-drainage; steep bed slope — may need falls; irrigates one side

Principles of alignment: command the maximum area with the shortest length; avoid villages, cemeteries, temples, valuable property; minimise cross-drainage works and balance cutting and filling; avoid rocky and unstable strata; keep curves gentle; place the head where the river is stable.

Canal losses

  • Evaporation — small (a few per cent) except in hot, dry, windy conditions.
  • Seepage — the major loss: absorption (wetting soil above the water table) and percolation (flow reaching the water table). Depends on soil permeability, water table depth, wetted perimeter, canal age (silting reduces loss) and velocity.
  • Seepage raises the water table in the command and is a main cause of waterlogging — lining reduces it (see Canal Lining).

Canal cross-section

  • Side slopes — in cutting roughly 1:1 (depending on soil); in filling flatter, about 1.5:1 to 2:1.
  • Freeboard — vertical distance between full supply level and top of bank; increases with discharge.
  • Banks — retain water, carry service road and inspection path; top width depends on discharge and road requirement.
  • Berms — horizontal strips at the full supply level or the natural ground level between the bank toe and water; strengthen banks, protect against erosion, allow future widening. In partial cutting, the berm width is chosen so that the silt deposited on the side slopes forms the stable regime slope (about ½ : 1).
  • Service road / inspection road on the bank; dowla — small bund on the road side for safety.
  • Spoil banks — excess excavated earth dumped along the canal when cutting exceeds filling.
  • Borrow pits — pits from which earth is taken when filling exceeds cutting; dug inside the canal bed (preferably) or at a safe distance outside the bank.
  • Balancing depth — the depth of cutting at which the earth from cutting exactly equals that required for the banks (economical section).

Sediment and regime

Alluvial canals carry silt. If velocity is too low, silt deposits (silting); if too high, the bed and banks erode (scouring). A canal is in regime when it neither silts nor scours over a hydrological cycle.

  • Initial regime — only the bed slope and depth adjust; width fixed by banks.
  • Final (true) regime — all variables (width, depth, slope, shape) adjusted to the discharge and silt.
  • Permanent regime — protected (lined) banks and bed; no further adjustment.

Kennedy's silt theory (1895)

R.G. Kennedy's observations on the Upper Bari Doab Canal (Punjab): silt is kept in suspension by the vertical eddies generated from the bed; so the silt-supporting power depends on the depth of flow (not width).

FormulaKennedy's equations (SI)

Critical (non-silting non-scouring) velocity:

= depth of flow (m); = critical velocity ratio (1.0 for Upper Bari Doab silt; > 1 for coarser silt, < 1 for finer silt).

Mean velocity for the given slope by Kutter's formula (with Chezy ).

Design procedure (for given , , , ): assume depth → from Kennedy → → find bed width (with side slopes ½ : 1) → compute and the velocity from Kutter's formula → compare with ; repeat until they agree.

Limitations:

  • Considers only eddies from the bed (ignores those from the sides).
  • No equation for bed slope — slope taken from Kutter's formula, which itself has limitations.
  • B/D ratio chosen arbitrarily; trial procedure lengthy.
  • Silt charge and grade are expressed only through the arbitrary ratio .
  • Based on data from one canal system.

Lacey's regime theory (1930)

Gerald Lacey found that regime channels have definite relations among discharge, velocity, hydraulic radius and slope. Silt is supported by eddies generated over the whole wetted perimeter.

Regime conditions assumed: constant discharge; constant silt charge; channel flowing in incoherent alluvium of the same grade that it transports (scoured and deposited with equal ease); unlimited incoherent alluvium.

FormulaLacey's regime equations (SI units)
  • Silt factor: ( = mean particle size in mm)
  • Velocity:
  • Hydraulic radius:
  • Area:
  • Wetted perimeter:
  • Bed slope:
  • Regime flow equation:
  • Normal scour depth (used for weirs and bridges):
  • Regime channel section: trapezoidal with side slopes ½ H : 1 V

Design procedure: find → → and → → solve for bed width and depth with ½ : 1 slopes → bed slope .

Drawbacks of Lacey's theory: true regime is rarely attained; the concept of incoherent alluvium is idealised; the equations do not treat silt charge and grade separately; the single silt factor cannot represent both; semi-circular shape idea and empirical constants based on limited data.

Kennedy versus Lacey

Kennedy Lacey
Eddies from the bed support silt Eddies from the whole perimeter
Critical velocity depends on depth only: Relations among , , , and
Uses Kutter's formula for velocity Own regime flow equation
No slope equation Gives slope
Trial-and-error design Direct design
= critical velocity ratio = silt factor
B/D ratio arbitrary Perimeter fixed by

Part 2 of 2

Farm Ponds & Small Earth Embankments

Last reviewed 1 Oct 2026 · 7 min read

Farm ponds

A farm pond is a small water body built on a farm to collect and store runoff (or pump water) for supplementary and life-saving irrigation, livestock and domestic use, fish culture, groundwater recharge and fire fighting. They are widely promoted in rain-fed regions under state programmes and schemes (check the current scheme and subsidy details).

Types

Type Description Suitable site
Excavated (dugout) pond Pit excavated in the ground; spoil banked around Flat or gently sloping land (below about 4 %), deeper soils, where runoff or a pumped supply reaches
Embankment (surface) pond Earth dam across a depression or a gully; storage upstream Sloping ground with a natural depression
Excavated + embankment (combined) Dugout with an embankment on the lower side Moderate slopes (about 4–8 %)
Spring-fed, dugout in groundwater Fed by seepage Where the water table is high
Lined pond Plastic-lined pond for high-seepage soils or drip supply Anywhere with a catchment

Site selection

  • Adequate catchment with a runoff yield (not too large — avoid heavy silt).
  • Soil with enough clay and low seepage (pervious sand or gravel is unsuitable unless lined); a deep, uniform soil layer for excavation.
  • Topography: a natural depression or the lowest corner, close to the area to be irrigated (so water can be applied by gravity or short pumping), and away from trees (roots, shade and leaf litter), buildings and flood-prone paths.
  • A stable spillway site (non-erodible).
  • Land ownership and cost.

Capacity design

FormulaCapacity

Required storage water demand during the use period + seepage loss + evaporation loss + silt allowance (about 10–20 % of capacity or as estimated):

Evaporation loss (pan evaporation × pan coefficient 0.7–0.8) × average water-spread area; seepage depends on the soil and lining.

Worked ExampleExample — pond capacity

A pond must supply 600 m³ for irrigation. Evaporation losses are estimated at 12 % and seepage at 15 % of the use, and the silt allowance is 10 % of the total capacity.

  • Use evaporation seepage m³.
  • With silt allowance: — about 850 m³.

Volume of an excavated pond

For a pond with rectangular top and bottom and constant side slopes, the prismoidal formula gives the volume exactly:

where is the depth, and is the area at mid-depth. Bottom dimensions top dimensions for a side slope horizontal : 1 vertical.

Worked ExampleExample — pond excavation volume

The top of a pond is 20 m × 15 m, depth m, side slope .

  • Bottom: m and m, so m².
  • Mid-depth dimensions: m and m, so m². m².
  • .

(A common check — the frustum formula gives the same result for the same shape. The excavation volume is also the earthwork that can build the embankment.)

Components of a pond

  1. Catchment and inlet channel (with a silt trap or settling basin).
  2. Excavated basin (with the stable side slope about 1:1 to 2:1 depending on soil — flatter in sandy soil).
  3. Embankment (for embankment ponds) — see below.
  4. Spillway (emergency overflow) — grassed/earthen or pipe, capacity to pass the design flood with freeboard.
  5. Outlet (pipe/siphon or pump) for withdrawal.
  6. Fencing, vegetation, safety steps, trash rack.

Seepage and evaporation control

Measure Notes
Compacted clay lining (about 30 cm) Cheap where clay is available; requires protection from cracking
Bentonite (soil mixing) Swells to seal sandy soils (about 5–10 % by mass)
Plastic film/geomembrane (LDPE, silpaulin ~250–300 gsm, HDPE) Very effective; covered with soil to protect from UV and animals
Cement, masonry or concrete lining Expensive; for small tanks
Soil sealing (sodium carbonate, chemical dispersants), asphalt Less common
Evaporation reduction Depth (reduces area-to-volume ratio), windbreaks, floating covers, monolayers, shade nets

Typical pond depth is 3–4 m (as it reduces evaporation per unit volume).