Recruitment guide

MECON Limited – Engineer posts (Civil, Civil & Structural and others) on Fixed Tenure – 159 posts: Notification PDF, Eligibility, Selection & How to Apply

MECON Limited

Last updated · read from the official notification

⏳ 5 days left · Last date 17 Oct 2026

MECON Limited, a Ministry of Steel PSU, is engaging 159 experienced professionals on a Full Time Fixed Tenure (contract) basis for projects across India (Advt. No. 2026/Cont/04). 56 posts are for civil engineers — site supervision of RCC and steel structures, structural steel fabrication and erection, civil QA/QC and RCC/steel design — at Assistant, Deputy and Additional Engineer level, with 2 to 10 years of experience. Selection is by personal interview only.

MECON Limited – Engineer posts (Civil, Civil & Structural and others) on Fixed Tenure – 159 posts — Overview

OrganisationMECON Limited
Posts / vacancies159 in all; 56 are Civil / Structural / Civil & Structural posts, and 27 more (Planning, Contracts, Projects) are open to engineers of any or several branches
QualificationB.E./B.Tech in Civil Engineering (some Civil & Structural posts also take Mechanical; one Deputy Engineer (Civil) post also takes a Civil diploma with 10 years' experience) plus post-qualification experience of 2 to 10 years, by post
PayConsolidated ₹45,050 (Assistant Engineer), ₹54,990 (Deputy Engineer), ₹67,860 (Additional Engineer) a month, plus site allowance 7.5% and other benefits
Age limitUpper age 50 years for General/EWS on 25.09.2026; OBC-NCL +3, SC/ST +5, PwD +10/13/15 years
Application fee₹500 for UR/OBC-NCL/EWS; SC/ST/PwD/Ex-servicemen and internal candidates exempt
Important datesOnline application: 03.10.2026 to 17.10.2026
LocationProject sites across India — Rampura Agucha Mines/Debari (Rajasthan), Bokaro, Vizag, Burnpur, Durgapur, Bhilai, Rourkela, Nagarnar, Paradip, Bangalore and others, by post
SelectionSelection is by interview only — there is no written test, so there is no syllabus to study for.

Who can apply

Needs work experience

Every post asks for post-qualification work experience — at least 2 years for Assistant Engineer, 5 years for Deputy Engineer and 9 to 10 years for Additional Engineer. Fresh graduates cannot apply.

Posts, qualification & pay

PostVacanciesQualificationExperienceAgePay
Addl. Engineer (Civil) — code 012B.E./B.Tech Civil10 years in civil construction of industrial projects50₹67,860
Addl. Engineer (Structural) — code 022B.E./B.Tech Civil10 years in structural steel fabrication & erection, incl. site supervision50₹67,860
Addl. Engineer (Quality) — code 071B.E./B.Tech Civil10 years in civil QA/QC for EPC/PMC projects50₹67,860
Dy. Engineer (Structural) — code 092B.E./B.Tech Civil5 years in structural steel fabrication & erection50₹54,990
Dy. Engineer (Quality) — code 141B.E./B.Tech Civil5 years in civil QA/QC (material testing, inspection, documentation)50₹54,990
Addl. Engineer (Civil & Structural) — code 202B.E./B.Tech Civil10 years in civil construction (civil buildings preferred)50₹67,860
Dy. Engineer (Civil & Structural) — code 215Full-time 4-year B.E./B.Tech Civil5 years, incl. 4 years of site supervision of RCC/steel structures50₹54,990
Addl. Engineer (Civil & Structural) — code 225Full-time 4-year B.E./B.Tech Civil9 years, incl. 7 years of site supervision of RCC/steel structures50₹67,860
Asst. Engineer (Civil & Structural) — code 284B.E./B.Tech Civil or Mechanical2 years in construction supervision / inspection / PMC of steel structures50₹45,050
Dy. Engineer (Civil & Structural) — code 294B.E./B.Tech Civil or Mechanical5 years, incl. 4 in steel-structure construction supervision / PMC50₹54,990
Addl. Engineer (Civil & Structural) — code 302B.E./B.Tech Civil or Mechanical9 years, incl. 7 in steel-structure construction supervision / PMC50₹67,860
Asst. Engineer (Civil & Structural) — code 3310Full-time 4-year B.E./B.Tech Civil or Mechanical2 years of site supervision of civil/structural work (industrial plant preferred)50₹45,050
Dy. Engineer (Civil) — code 361B.E./B.Tech Civil5 years of civil works in heavy industry — earthwork, foundations, piling, flexible and rigid pavements50₹54,990
Deputy Engineer (Civil) — code 392Diploma in Civil (10 years' site experience) or B.E./B.Tech Civil (5 years)Construction-site experience50₹49,140 (diploma) / ₹54,990 (degree)
Dy. Engineer (Civil) — code 4110B.E./B.Tech Civil5 years in RCC / steel structures design50₹54,990
Asst. Engineer (Civil & Structural) — code 501B.E./B.Tech Civil2 years in steel-structure design with STAAD/ETABS and AutoCAD50₹45,050
Asst. Engineer (Civil & Structural) — code 512B.E./B.Tech Civil2 years in RCC design with STAAD/ETABS and AutoCAD50₹45,050
Planning, Contracts and Projects posts (codes 04, 13, 40, 42) — also open to civil engineers27B.E./B.Tech in any engineering (04, 13, 40) or Mechanical/Electrical/Civil (42)5 to 10 years in planning (Primavera/MS Project), tendering and billing, or project management50₹54,990 – ₹67,860

Important dates

  • Online applications open on 03.10.2026 and close on 17.10.2026.
  • Age and post-qualification experience are counted as on 25.09.2026.

Source: page 1 of the official notification.

Selection process

  • Selection is by personal interview; MECON may change the mode of selection if required.
  • The list of candidates called for interview, with date, time and venue, is put on MECON's website and also sent by e-mail.
  • Documents are checked when a shortlisted candidate reports for the interview; a claim that is not substantiated means no interview and no travelling allowance.
  • The final selection list is put on the website, followed by document verification and a medical examination.

Source: page 11 of the official notification.

Pay and benefits

  • Consolidated pay as listed for each post, with a site allowance of 7.5% of pay at project sites and a metro allowance of 2.5% in metro cities.
  • Annual increment of 3% of the consolidated pay.
  • Medical care at Ispat Hospital if posted at Ranchi; elsewhere a retainer doctor, and Mediclaim premium reimbursed up to ₹15,000 a year (₹4 lakh floater cover).
  • Company accommodation where available, otherwise HRA at 5% of pay.
  • Leave: 12 days casual, 18 days earned (accumulates to 45), 14 days half-pay a year; Group Personal Accident cover of ₹25 lakh.

Source: page 8 of the official notification.

Contract period and posting

  • The contract period is 1 to 5 years depending on the post; the offer is made for 1 year at a time and renewed yearly on satisfactory performance.
  • Posting is post-wise: codes 01–16 Rampura Agucha Mines/Debari (Rajasthan), 20 Bangalore/Nasik, 21–22 Bokaro/Vizag, 28–30 Burnpur/Durgapur, 33 Burnpur/Bhilai/Rourkela/Bacheli/Mumbai and other sites, 35–37 Nagarnar, 38–39 Paradip, 41 Burnpur/Bhilai, 48–59 Bangalore.
  • Joining is subject to being found medically fit.

Source: page 12 of the official notification.

What counts as experience

  • Only full-time work on a regular salary in the field named for the post counts; freelance and entrepreneurial work do not.
  • Training as a Management / Executive / Graduate Trainee in a PSU, and apprenticeship under the Apprentices Act, are counted.
  • Articleship, internship, academic projects, teaching and research are not counted.
  • Experience certificates are needed for every past job (dates, duties, relevance); for the present job, an appointment letter or ID card plus the last 3 months' pay slips. A self-declaration is not accepted.

Source: page 9 of the official notification.

Age relaxation and fee

  • Upper age limit 50 years for General/EWS; relaxed by 3 years for OBC-NCL, 5 years for SC/ST, 10/13/15 years for PwD (UR/OBC/SC-ST), 5 years for J&K domicile (1980–89), and for ex-servicemen as per Government of India rules.
  • Fee ₹500 for UR, OBC-NCL and EWS, paid online only; SC, ST, PwD, ex-servicemen and internal candidates do not pay. After paying, click 'Verify' so the application shows as Submitted.

Source: page 10 of the official notification.

How to apply

  • Apply online only, at MECON's website: Careers → Career Opportunities → Apply Online.
  • Upload a photograph and signature (JPG, up to 40 KB each) and all certificates as one self-attested PDF of up to 1 MB: age proof, degree and all mark sheets, experience proofs, PAN and Aadhaar (Aadhaar is mandatory), and category/PwD/ex-servicemen certificates where applicable.
  • Employees of government, PSUs or autonomous bodies must apply through proper channel or bring a No Objection Certificate to the interview.
  • Bring all original documents and a hard copy of the online application to the interview; queries go to recruit@meconlimited.co.in.

Source: page 13 of the official notification.

MECON Limited – Engineer posts (Civil, Civil & Structural and others) on Fixed Tenure – 159 posts — Official Notification PDF

MECON Limited — Recruitment for contractual engagement of experienced professionals on Full Time Fixed Tenure (FTFT) basis, Ref. Adv. No. 2026/Cont/04. Read it fully before you apply.

Original on the official website: https://careers.meconlimited.co.in/api/download?file=20261001_192747_Final%20Advertisment_%20FTFT%20_%20159%20_Final%20Posts.pdf

Interview Preparation — 100 questions with answers

MECON Limited (Adv. 2026/Cont/04, FTFT) — Civil, Structural and Civil & Structural Engineers: Assistant / Deputy / Additional Engineer

MECON fills these fixed-tenure posts by personal interview alone, so the interview board will test the work the advertisement describes: supervising RCC and steel construction in steel plants, fabrication and erection, QA/QC, design, and the planning and contract side of EPC/PMC jobs. The 100 questions below follow those duties. Read each answer, then say it in your own words with an example from your own projects.

Built from what the notification asks for

  • Site supervision of RCC and steel structural construction in industrial projects (post codes 01, 20, 21, 22, 33)
  • Structural steel fabrication, erection, inspection and PMC services for industrial / infrastructure steel structures (02, 09, 28, 29, 30)
  • Civil QA/QC for EPC/PMC projects — material testing, site inspection, documentation, compliance with drawings, codes and specifications (07, 14)
  • Design of RCC and steel structures with STAAD / ETABS and AutoCAD (41, 50, 51)
  • Heavy-industry civil works in an integrated steel plant — earthwork with heavy machinery, open foundations, piling, flexible and rigid pavements (36)
  • Project planning with Primavera / MS Project and contracts, tendering and billing (04, 13, 40, 42 — open to civil engineers)
  • Selection by personal interview only (Clause 11 of the advertisement)

About the role and your experience (8)

1.Tell us about your experience and how it matches this post.

Answer in a fixed order: the projects you worked on (client, type, value or size), your exact role, the quantities or scope you handled (for example 4,000 m³ of concrete or 1,200 t of structural steel), one technical problem you solved, and what you would bring to MECON. Match your words to the post code you applied for — RCC and steel site supervision, QA/QC or design — and keep it under two minutes.

2.What do you know about MECON Limited?

MECON is a Government of India enterprise under the Ministry of Steel, a Schedule 'A' Miniratna with its head office at Doranda, Ranchi. It provides design, engineering, consultancy and EPC services across the full project life cycle, has executed over 4,000 consultancy and EPC assignments, and has played a central role in building and expanding India's iron and steel plants. It also works in power, oil and gas, infrastructure and mining.

3.What is the difference between working for a PMC consultant and working for a contractor?

A contractor's engineer is responsible for executing the work — arranging labour, material and machinery and meeting the schedule. A PMC (project management consultant) engineer works for the owner: checks that the work follows drawings, specifications and codes, inspects and approves stages, certifies measurements and bills, monitors progress against the schedule, flags risks and coordinates between contractors. MECON's site roles are largely on the PMC side, so quality control and documentation matter most.

4.Explain EPC, PMC and item-rate contracts.

In an EPC (engineering, procurement and construction) contract one party designs, buys and builds for a lump-sum price and carries most of the design and quantity risk. In a PMC arrangement a consultant manages the project for the owner without executing it. In an item-rate contract the owner gives the design and a bill of quantities, and the contractor is paid quoted rates for the quantities actually executed, so quantity risk stays with the owner.

5.How do you plan and record a day's work at site?

Start from the look-ahead schedule: list the day's activities, check that drawings, materials, manpower, machinery and permits are ready, and hold a short morning meeting including a safety talk. Inspect stages as they are completed, clear pours and erection steps on checklists, and note hindrances. At the end of the day prepare the daily progress report — quantities done, resources deployed, tests taken, issues and the next day's plan.

6.What will you do if a contractor executes work that deviates from the approved drawing?

Stop the activity if continuing would make it worse, record the deviation with photographs and measurements, and issue a written site instruction or non-conformance report. Check whether it affects safety or strength; if it might, refer it to the designer for a decision (accept, repair or demolish). Get the corrective action done, verify it, close the NCR, and analyse why it happened so the same mistake is not repeated.

7.The architectural and structural drawings show different dimensions for a beam. What do you do?

Do not let the work proceed on a guess. Mark the clash on both drawings, raise a technical query (RFI) to the design team through the proper channel and ask for a revised drawing or written clarification. Meanwhile reschedule the crew to other work so time is not lost. Once the reply comes, make sure the superseded drawings are withdrawn from site so nobody uses the old revision.

8.Which units of an integrated steel plant involve major civil and structural work?

Raw material handling (yards, wagon tipplers, conveyors, junction houses), coke ovens and by-product plant, sinter plant, blast furnace, steel melting shop (converters, ladle furnaces, casters), rolling mills, oxygen plant, power plant, water treatment and utilities. Typical civil items are heavy machine foundations, deep pits and tunnels, conveyor galleries and trestles, large steel buildings with crane girders, chimneys, water-retaining structures and heavy-duty roads.

RCC construction and site supervision (18)

9.What do you check before allowing a concrete pour?

Formwork line, level, dimensions, plumb and rigidity, tight joints and release agent; reinforcement against the drawing and bar bending schedule (diameter, spacing, laps, chairs and cover blocks); embedments, inserts, sleeves and pockets fixed; construction joints cleaned and prepared; area clean of debris; concrete grade and quantity confirmed, pump or vibrators and standby ready; lighting and curing arrangements. Only then sign the pour card.

10.What nominal cover does IS 456:2000 require?

IS 456 relates nominal cover to exposure: 20 mm for mild, 30 mm for moderate, 45 mm for severe, 50 mm for very severe and 75 mm for extreme exposure. Footings need at least 50 mm, and longitudinal bars in columns at least 40 mm. Cover protects steel from corrosion and fire; at site it is ensured with proper-size cover blocks of concrete or mortar at close spacing.

11.When can formwork be removed as per IS 456?

For ordinary Portland cement in normal weather IS 456 gives: vertical faces of columns, walls and beams 16 to 24 hours; slab soffits with props left under 3 days; beam soffits with props left under 7 days; props under slabs spanning up to 4.5 m 7 days and over 4.5 m 14 days; props under beams and arches spanning up to 6 m 14 days and over 6 m 21 days. Cold weather or other cements need longer.

12.How long and how should concrete be cured?

IS 456 asks for at least 7 days of moist curing for ordinary Portland cement concrete, extended to at least 10 days where mineral admixtures or blended cements are used, and longer in hot, dry weather. Methods are ponding, wet hessian or gunny bags kept moist, sprinkling, impermeable sheets or a curing compound. Curing should start as soon as the surface has set, without drying in between.

13.Where are construction joints placed and how are they treated?

They are placed where shear is small and the joint is easy to make — in beams and slabs near the middle third of the span, in columns a little below the beam soffit or just above the slab, at right angles to the main reinforcement. Before the next pour the old surface is roughened, laitance removed, cleaned with air and water, kept saturated surface-dry, and a bonding grout or agent is applied immediately before concreting.

14.What lap length do you provide and what are the rules for laps?

IS 456 gives lap length in flexural tension as the development length Ld or 30 bar diameters, whichever is more; in direct tension 2Ld or 30φ; in compression the compression development length but not less than 24φ. Laps should be staggered so that not more than half the bars are lapped at one section, kept away from points of maximum stress, and bars larger than 36 mm should be welded or mechanically coupled.

15.How is development length calculated?

Ld = φ σs / (4 τbd), where φ is the bar diameter, σs the stress in the bar at the section (0.87 fy at the limit state) and τbd the design bond stress for the concrete grade. IS 456 lists τbd for plain bars (for example 1.2 N/mm² for M20), increases it by 60 percent for deformed bars and by a further 25 percent for bars in compression. Higher grades of concrete reduce Ld.

16.What is a bar bending schedule and how do you check it?

A BBS lists every bar mark with its member, diameter, shape, number and cutting length and the total weight by diameter. Checking means comparing it with the structural drawing (spacing, laps, anchorage, cover) and checking cutting lengths, which include hooks and bends and deduct bend allowances — commonly about 1d for a 45° bend, 2d for 90° and 3d for 135°. It controls cutting, wastage and steel billing.

17.What causes honeycombing and how do you repair it?

Causes are poor compaction, congested reinforcement, too stiff a mix, segregation from dropping concrete from a height, and grout leaking from formwork joints. Minor honeycombing is cut back to sound concrete, cleaned, wetted and filled with polymer-modified mortar after a bonding coat. Deep or extensive honeycombing is examined by the designer and repaired by micro-concrete, pressure grouting or, if strength is in doubt, by testing and even recasting the member.

18.What is a cold joint and how do you avoid it?

A cold joint forms when fresh concrete is placed against concrete that has already started setting, leaving a weak and leaky plane. It is avoided by planning the pour size and supply so each layer is covered within its setting time, keeping standby pump and batching capacity, using a retarder in long or hot-weather pours, and — if supply fails — stopping at a planned location and forming a proper construction joint.

19.What slump values would you specify for different works?

IS 456 suggests about 25 to 75 mm for lightly reinforced work such as mass concrete and footings, 50 to 100 mm for heavily reinforced slabs, beams, walls and columns, and 75 to 100 mm for pumped concrete. Tremie concrete for bored piles needs much higher workability — IS 2911 calls for a slump of about 150 to 200 mm. The slump test itself is done as per IS 1199.

20.How many cube samples are taken for a pour as per IS 456?

IS 456 sampling frequency: 1 sample for 1–5 m³, 2 for 6–15 m³, 3 for 16–30 m³, 4 for 31–50 m³, and for 51 m³ and above, 4 plus one more for each additional 50 m³ or part. Each sample gives three 150 mm cubes, cured and tested at 28 days (7-day cubes are often added for early information). Acceptance is checked on group means and individual results as per IS 456.

21.How is the target mean strength found in concrete mix design?

As per IS 10262 the target mean strength is f'ck = fck + 1.65 s, where s is the standard deviation of the plant's results. When site data is not available, assumed values are used — 4 N/mm² for M20 and M25 and 5 N/mm² for M30 and above in the 2019 code. The design then fixes water-cement ratio from durability and strength, water content from workability, and the aggregate proportions.

22.What does IS 456 say about the maximum water-cement ratio and minimum cement content for RCC?

For reinforced concrete IS 456 Table 5 gives: mild exposure — 300 kg/m³ cement, w/c 0.55, minimum M20; moderate — 300 kg/m³, 0.50, M25; severe — 320 kg/m³, 0.45, M30; very severe — 340 kg/m³, 0.45, M35; extreme — 360 kg/m³, 0.40, M40. Steel plant areas with fumes, spillage or water are often treated as severe exposure.

23.What precautions do you take in hot-weather concreting?

Keep the concrete temperature low: shade and sprinkle aggregates, use chilled water or ice, schedule pours for early morning or night, and use a retarding plasticiser. Reduce delay between mixing and placing, shade the pour area, wet the formwork and sub-base, and start curing immediately — fog spraying or a curing compound — so that plastic shrinkage cracks do not form on slabs.

24.What special care is needed for mass concrete in large machine foundations?

Heat of hydration makes the core much hotter than the surface, and the difference causes thermal cracks. Control it by using blended cement or fly ash, lower cement content, cooled ingredients and placing temperature limits, pouring in planned lifts and sequence, insulating the surfaces and monitoring temperatures with embedded sensors. Foundation bolts, pockets and embedments are fixed with templates and checked by survey before and after the pour.

25.How do you construct and test a water-retaining structure?

Design and construction follow IS 3370 — dense concrete, controlled cracking, adequate cover, PVC water-stops at construction and expansion joints, and careful compaction near joints. After curing, the tank is filled in stages and kept full for a settling period, then the water level is monitored over several days for the drop allowed in the specification while the outer faces are checked for damp patches. Leaks are sealed and the test repeated.

26.How do you grout the base plates of columns and equipment?

After alignment and levelling on packers or levelling nuts, the foundation top is chipped, cleaned and kept saturated surface-dry, shuttering is fixed around the plate with a pouring head, and a non-shrink, free-flowing cementitious grout is mixed as per the manufacturer and poured from one side only so air escapes. The grout is cured, and nuts are fully tightened only after it gains the required strength.

Concrete and materials QA/QC (14)

27.What is a Quality Assurance Plan (QAP) or Inspection and Test Plan (ITP)?

It is the agreed document that lists, activity by activity, what is to be inspected or tested, the reference code or specification, the acceptance criteria, the frequency, the records to be kept and who inspects — with hold points (work cannot proceed without the client's inspection) and witness points. At site every check is recorded against the ITP so that quality can be proved later.

28.Which tests are done on cement at site and in the lab?

Under IS 4031: normal consistency, initial and final setting time, soundness by Le Chatelier or autoclave, fineness, and compressive strength on 70.6 mm mortar cubes at 3, 7 and 28 days. At site the manufacturer's test certificate is checked for each lot, bags are checked for date of manufacture and lumps, and storage is on a raised platform away from moisture, used first-in first-out.

29.Which tests are done on fine and coarse aggregates?

As per IS 2386 and IS 383: sieve analysis for grading and zone, silt and clay content, flakiness and elongation indices, specific gravity and water absorption, bulking of sand for volume batching, and for coarse aggregate the aggregate impact and crushing values. IS 383 limits the crushing value to 45 percent for concrete other than wearing surfaces and 30 percent for wearing surfaces such as roads and floors.

30.How do you check TMT reinforcement bars?

Each lot is checked against the mill test certificate (grade, heat number, chemistry) and sampled for testing as per IS 1786: yield or 0.2 percent proof stress, tensile strength, elongation, bend and rebend tests, and mass per metre. For Fe 500D the code needs higher ductility than Fe 500 — a tensile-to-yield ratio of at least 1.10 and elongation of at least 16 percent. Bars are stored off the ground and protected from rust.

31.What are the requirements for water used in concrete?

IS 456 requires water fit for drinking in general, free from oils, acids, alkalis, salts, sugar and organic matter, with pH not less than 6. Limits apply to solids such as chlorides and sulphates, and a sample is tested when the source is doubtful — by comparing setting time and strength of cement mixed with it against distilled water. The same quality is needed for curing water.

32.Cube results have failed. What will you do?

First check the cube records — sampling, curing, testing and calculation — for errors. If the results stand, assess the concrete in place by non-destructive tests (rebound hammer and ultrasonic pulse velocity) and then by cores. As per IS 456 the concrete is acceptable if the average strength of three cores is at least 85 percent of the cube strength for the grade and no single core is below 75 percent; otherwise the designer decides on load test, strengthening or replacement.

33.How do you handle a non-conformance report (NCR)?

Raise the NCR in writing with the exact location, the requirement violated and evidence. The contractor proposes correction and corrective action; the engineer or designer approves the disposition — use as is, repair, rework or reject. After the work is done it is verified and the NCR is closed with records. NCRs are tracked in a register and analysed for repeat causes in the quality review.

34.Why is calibration of equipment important and what do you calibrate at site?

Test results are only valid if the instruments are accurate. Items that need calibration certificates traceable to national standards include the compression testing machine, weighing scales and batching plant load cells, slump cones and moulds (dimension checks), thermometers, torque wrenches, dial gauges, survey instruments such as total stations and levels, and DFT and coating gauges. A calibration register shows due dates, and overdue equipment is withdrawn.

35.What do you inspect at a ready-mix concrete plant or site batching plant?

Approved mix design and trial results, storage and moisture of aggregates, cement and admixture approvals and their test certificates, calibration of weigh batchers and water meters, the batching record printout for each truck, mixer condition, and the plant's own testing. At delivery each truck's challan is checked for grade, quantity, time of batching and admixture, the slump is checked, and concrete beyond the allowed time is rejected.

36.How do you compact concrete properly with needle vibrators?

Place concrete in layers of about 300 to 450 mm, insert the needle vertically at regular spacing so the zones of action overlap, let it sink into the previous layer, hold it until air bubbles stop rising and a thin film of paste appears, and withdraw slowly. Do not use the vibrator to move concrete sideways, avoid touching reinforcement and formwork, and avoid over-vibration that causes segregation and bleeding.

37.Which records do you maintain as a QA/QC engineer?

Approved QAP/ITP, material inspection and test certificates, material test registers (cement, steel, aggregates, water, admixtures), mix designs and trial results, pre-pour checklists and pour cards, cube test register with results, NCR and site instruction registers, calibration register, third-party test reports, and as-built and inspection records. Together they let the owner prove that every element meets the specification.

38.What is third-party inspection and when is it used?

Third-party inspection is testing or inspection by an independent accredited agency that is neither the contractor nor the owner. It is used for critical items such as structural steel fabrication at the vendor's works, welding NDT, cement and steel lots, pile load and integrity tests, and for confirming test results that are disputed. The agency follows the approved QAP and issues signed reports and inspection release notes.

39.How do you test floors and roof slabs for leakage and finish?

Roof slabs and waterproofed areas are pond-tested: drains are blocked and water held for about 24 to 72 hours as specified, and the soffit is checked for damp patches. Floors are checked for level and slope with a straight edge and level, for hollow sounding of tiles or toppings, and industrial floors for flatness, surface hardness and joint sealing as per the specification.

40.What non-destructive tests are used on hardened concrete?

The rebound hammer gives surface hardness that relates to strength; ultrasonic pulse velocity checks uniformity and detects cracks and voids — both now covered in IS 516 (formerly IS 13311). A cover meter or rebar locator measures cover and bar positions; half-cell potential indicates corrosion risk. NDT is used for comparison and screening; strength is confirmed by testing cores.

Structural steel fabrication and erection (16)

41.Describe the stages of structural steel fabrication.

Approved fabrication and shop drawings, material receipt with mill test certificates and heat numbers, marking and cutting (gas, plasma or saw), edge preparation and drilling, fit-up and tack welding, welding to the approved WPS, NDT, straightening and dimensional checks, trial assembly where needed, surface preparation by blasting, painting with the specified system, piece marking with erection marks, and dispatch with packing lists.

42.What are WPS, PQR and WPQ?

A WPS (welding procedure specification) states how a weld is to be made — process, base and filler materials, joint preparation, position, current, voltage, speed, preheat. A PQR (procedure qualification record) is the record of test welds proving that the WPS gives sound welds with the required properties. A WPQ (welder performance qualification) proves that a particular welder can make that weld. Site welding is allowed only with qualified procedures and welders.

43.Name common weld defects and the tests used to find them.

Common defects are porosity, slag inclusion, lack of fusion, incomplete penetration, cracks, undercut, overlap and wrong weld size. Visual inspection with gauges is done on all welds; dye penetrant (DPT) and magnetic particle tests (MPI) find surface cracks; ultrasonic (UT) and radiographic (RT) tests find internal defects in butt welds. The extent of NDT is fixed by the specification and the QAP.

44.What is the difference between black bolts and HSFG bolts?

Ordinary (black) bolts transfer force by bearing and shear of the bolt shank and are snug-tightened. High strength friction grip (HSFG) bolts are tensioned to a high pre-load so the clamped plates transfer load by friction, giving a slip-resistant joint for fatigue and vibration — as in crane girders and heavy industrial frames. HSFG installation follows IS 4000, with tensioning by part-turn, calibrated wrench or direct tension indicators, and the faying surfaces must be prepared as specified.

45.What is the normal erection sequence of a steel industrial building?

Check foundations and anchor bolts by survey, set levelling nuts or packers, erect columns and temporarily guy them, erect tie beams and vertical bracing in the first braced bay to make it stable, then the crane girders, roof trusses or rafters, roof bracing and purlins; align and plumb each bay, tighten connections, grout the base plates, then side girts and roof and wall sheeting. Each stage is checked before the next.

46.How do you check foundation bolts before erection?

Bolts should have been fixed with rigid templates before concreting. Before erection, check by total station or tape from grid lines the position of each bolt group, the projection and level of the top of the foundation and bolts, threads (clean, greased, undamaged), verticality, and sleeve clearances where sleeves are provided. Errors are recorded and corrected with the designer's approval — not by bending bolts or flame-cutting holes in base plates.

47.Which Indian Standards cover fabrication and erection tolerances?

IS 7215 gives tolerances for fabrication of steel structures (lengths, straightness, squareness, hole positions) and IS 12843 gives tolerances for erection (column plumb and position, levels of beams and crane girders, alignment). IS 800:2007 covers fabrication and erection requirements generally. Project specifications often tighten these values for crane girders and equipment-supporting steel, so always check the contract specification.

48.How is surface preparation and painting of structural steel inspected?

Blasting cleanliness is checked against the specified grade (commonly Sa 2½ to ISO 8501-1) and the surface profile with a comparator or replica tape, along with dust and salt contamination and ambient conditions — the steel should be at least 3 °C above the dew point. Each coat is checked for dry film thickness with a calibrated gauge, plus adhesion and visual defects, and touch-up is done after erection.

49.What checks are critical for crane girders and crane rails?

Span between rails, rail level along the length and across the span, alignment and straightness of the rail, splice joints, rail clips and pads, girder camber, stiffeners, end stops and the HSFG bolting of connections. Errors cause crane wheel wear and skewing, so the crane rail survey is done after erection and before handover against the tolerances in the specification.

50.How do you plan a heavy lift such as a conveyor gallery?

Prepare a lifting plan: weight of the lift with rigging, centre of gravity, crane selection from its load chart at the required radius and boom length, ground bearing capacity and outrigger mats, rigging design (slings, shackles, spreader beams with certificates), lifting points, weather and wind limits, exclusion zone, tag lines, and a signalman. A trained supervisor conducts the lift and a pre-lift meeting is held.

51.Which steel grades are used for structures and how are they verified?

IS 2062 hot-rolled structural steel is used, mainly E250 and E350 in qualities A, BR, B0 and C, which differ in impact (toughness) requirements. Each lot is verified by the mill test certificate (chemistry, yield and tensile strength, elongation, impact values), heat number marking on the material, and sample testing where the QAP requires. Tubes and hollow sections follow IS 1161 and IS 4923.

52.How do you control distortion during welding?

Use correct joint design with minimum weld volume, balanced welding sequences (backstep, alternate sides), proper fit-up without excess gaps, jigs and fixtures or strongbacks, tack welding at close intervals, presetting members to counter expected movement, and preheat where needed. After welding, straightening is done by controlled heating or pressing within the limits of the specification.

53.What safety measures do you enforce during steel erection?

Valid work permits, competent riggers and certified cranes and lifting tackle, full-body harnesses with lifelines and anchor points, safety nets where needed, barricaded exclusion zones under lifts, tag lines, no working under suspended loads, temporary bracing until members are permanently connected, safe access by ladders and platforms, and stopping work in high wind or poor visibility.

54.How is structural steel measured for payment?

As per the contract, normally by weight calculated from the approved fabrication drawings using standard sectional weights from the Indian Standard tables, with plates by area times thickness times density. Bolts, welds, wastage and rolling margin are usually not paid separately unless the contract says so. The method of measurement in IS 1200 or the contract's own clauses governs.

55.What is the inspection release note (IRN) process for steel fabricated at a vendor's works?

The vendor offers items for inspection as per the approved QAP. The inspector (client, PMC or third party) verifies material certificates, witnesses stage inspections and tests, checks dimensions, welding, NDT reports and painting, and on acceptance issues an IRN allowing dispatch. Items without an IRN are not accepted at site. Deviations are recorded and resolved through concessions or NCRs.

56.How do you check alignment and plumb of erected columns?

Using a total station or theodolite in two perpendicular directions, or plumb bobs for short members, check each column's position on the grid and its verticality, and use a level for base and bracket levels. Columns are adjusted with turnbuckles, guys and wedges before bracing is tightened and base plates are grouted. Readings are recorded against the erection tolerances of IS 12843 or the specification.

Structural design (RCC and steel) (14)

57.What partial safety factors are used in limit state design?

In IS 456 the load factor for dead plus imposed load at the ultimate limit state is 1.5, with other values for combinations with wind or earthquake (for example 1.2 for DL + LL + WL/EL). Material factors are 1.5 for concrete and 1.15 for steel. In IS 800:2007 the partial factor for resistance governed by yielding is γm0 = 1.10 and for ultimate (rupture) γm1 = 1.25.

58.Which Indian Standards are used to calculate loads on an industrial structure?

IS 875 Part 1 for dead loads (unit weights), Part 2 for imposed loads, Part 3 for wind, Part 4 for snow and Part 5 for special loads and load combinations; IS 1893 Part 1 and Part 4 for earthquake forces on buildings and industrial structures. Crane loads, equipment loads, material loads on conveyors and dynamic loads come from vendors and process data.

59.How do you model a steel building in STAAD.Pro?

Create the geometry from the grid, assign section properties and material, define supports (pinned or fixed according to the base design), member releases for pinned connections, and bracing as truss members where appropriate. Define load cases — dead, live, crane, wind in several directions, seismic — and combinations as per the codes, run the analysis (P-delta if sway is significant), check deflections and drifts, then run member design to IS 800 and review the utilisation ratios.

60.What are the deflection limits for RCC members in IS 456?

The final deflection of beams and slabs, including creep and shrinkage effects, should not normally exceed span/250. The deflection that occurs after partitions and finishes are built should not exceed span/350 or 20 mm, whichever is less. In design these are usually satisfied by the span-to-effective-depth ratios (basic values 7 for cantilevers, 20 for simply supported and 26 for continuous spans) with modification factors.

61.When is an RCC column treated as short or slender?

As per IS 456, a column is short when its effective length to least lateral dimension ratio is less than 12, and slender (long) when it is 12 or more, in which case additional moments due to slenderness are added. Effective length depends on end restraint. The code also requires a minimum eccentricity for all columns, of unsupported length/500 plus lateral dimension/30, but not less than 20 mm.

62.What minimum and maximum reinforcement does IS 456 specify?

Beams: minimum tension steel As/bd = 0.85/fy, maximum tension or compression steel 4 percent of bD. Slabs: minimum 0.12 percent of the gross area with high-yield bars (0.15 percent with mild steel). Columns: longitudinal steel between 0.8 and 4 percent of the gross area as a practical limit (6 percent is the code maximum), with at least four bars of 12 mm in a rectangular column.

63.What are the main design checks for a machine foundation?

Static checks — bearing pressure, settlement, overturning and sliding — and dynamic checks: the natural frequency of the foundation-soil system should stay well away from the machine's operating frequency (avoid resonance, commonly by at least about 20 percent) and vibration amplitudes must be within the limits for the machine and nearby equipment. Block, wall or frame foundations are chosen accordingly; IS 2974 gives the code of practice.

64.How is basic wind load calculated as per IS 875 Part 3?

The design wind speed Vz = Vb × k1 × k2 × k3 × k4, where Vb is the basic wind speed of the location, k1 the risk coefficient, k2 the terrain, height and size factor, k3 the topography factor and k4 the importance factor for cyclonic regions. The design wind pressure pz = 0.6 Vz², and further factors for directionality, area averaging and combination apply before using pressure coefficients for the building.

65.How is design base shear calculated as per IS 1893?

VB = Ah × W, where W is the seismic weight (dead load plus the required fraction of imposed load) and Ah = (Z/2) × (I/R) × (Sa/g). Z is the zone factor, I the importance factor, R the response reduction factor of the structural system, and Sa/g the spectral acceleration coefficient from the response spectrum for the fundamental period and soil type. The base shear is then distributed over the height.

66.What is section classification in IS 800:2007?

Sections are classified by the width-to-thickness ratio of their plate elements: plastic (class 1) can form a plastic hinge and rotate; compact (class 2) reaches plastic moment but with limited rotation; semi-compact (class 3) reaches only the first yield moment; slender (class 4) buckles locally before yield. The class decides whether plastic or elastic section capacity is used in design.

67.What stability checks does IS 456 require for foundations and retaining structures?

IS 456 requires the restoring moment against overturning to be not less than 1.2 times the overturning moment from characteristic dead load plus 1.4 times that from imposed load, and a factor of safety against sliding of at least 1.4 under the most unfavourable combination. Bearing pressure must stay within the safe bearing capacity, and uplift and flotation are checked where the water table is high.

68.What do you check when reviewing a vendor's or contractor's design drawing?

That it uses the latest approved input — loads, layout and equipment data; the codes and grades specified; member sizes and reinforcement matching the calculations; connection details, anchor bolts and embedments; cover, laps and detailing rules; clashes with other disciplines (pipes, cable trays, openings); constructability; and title block, revision and notes. Comments are recorded and tracked until the drawing is approved for construction.

69.When would you use ETABS instead of STAAD.Pro?

ETABS is built for buildings — floor diaphragms, storeys, shear walls and code-based seismic and wind design of multi-storey frames — so it is efficient for RCC buildings. STAAD.Pro is a general-purpose program well suited to industrial steel structures, trusses, pipe racks, conveyor galleries and mixed systems. Either way the engineer must understand the model and check the results by hand on key members.

70.How do you design a simple bolted shear connection in steel?

Find the design force, choose bolt grade and diameter, and take the bolt value as the lower of shear capacity (on the threads or shank as applicable) and bearing capacity on the thinner plate as per IS 800. Number of bolts = force ÷ bolt value, arranged with the minimum pitch, edge and end distances. Then check the connected plates for tension or shear yielding, rupture and block shear.

Foundations, piling and earthwork (11)

71.What information do you take from a geotechnical investigation report?

The borehole logs with soil and rock layers, SPT N values, ground water level, laboratory results (grain size, Atterberg limits, shear strength, consolidation, chemical aggressiveness of soil and water), safe bearing capacity and settlement for given foundation sizes and depths, pile capacities for recommended pile types and lengths, and special recommendations such as expansive soil treatment or sulphate-resisting cement.

72.Describe the construction of a bored cast-in-situ pile.

Set out the pile point, install the guide casing, bore to the founding level using bentonite slurry or a temporary casing to keep the hole stable, check depth and verticality, flush the bore to remove debris, check slurry properties, lower the reinforcement cage with cover spacers, and concrete continuously by tremie from the bottom up. Concrete is overpoured above cut-off level so that weak concrete can later be chipped off.

73.Why is bentonite slurry used in piling and what is checked?

Bentonite slurry stabilises the borehole by its hydrostatic pressure and by forming a thin filter cake on the walls, and it keeps cuttings in suspension. Its density, Marsh cone viscosity, pH and sand content are checked when fresh and again from the bottom of the bore just before concreting, against the limits in IS 2911 and the specification, because contaminated slurry leads to soft toe and inclusions in the pile.

74.What is the difference between an initial and a routine pile load test?

An initial test is done on a test pile before the working piles, to establish the safe load and behaviour, and is usually loaded to about 2.5 times the expected working load or until failure. A routine test is done on selected working piles to confirm their performance and is loaded to about 1.5 times the working load, without damaging the pile. Both follow IS 2911 Part 4.

75.What is a pile integrity test?

It is a low-strain test: a small hammer blow is applied to the pile head and a sensor records the reflected stress wave. Changes in the signal show cracks, necks, bulges, voids or soil inclusions and indicate the pile length. It is fast and cheap, so many piles can be tested, but it does not give load capacity — that comes from static or high-strain dynamic load tests.

76.What rules do you follow during tremie concreting of piles?

Use a watertight tremie with a plug, start with the tremie at the bottom so the first concrete displaces the slurry upward, keep the tremie embedded in the fresh concrete throughout (never pull it out of the concrete), use high-slump cohesive concrete, pour continuously without long breaks, record the concrete level against volume poured, and overpour above cut-off level.

77.How do you control compaction of earth fill?

Use approved soil, find its maximum dry density and optimum moisture content by the Proctor test (IS 2720 Part 7 or 8), spread in layers of about 200 to 250 mm loose thickness, bring moisture close to OMC, and compact with suitable rollers. Field dry density is measured by core cutter (IS 2720 Part 29) or sand replacement (Part 28), and each layer must reach the specified percentage of MDD, often 95 percent or more.

78.What dewatering methods are used for deep foundations and pits?

Open sump pumping for small inflows in stable soils; well points in sandy soils for moderate depths; deep wells with submersible pumps for large depths and high inflow; and cut-off methods such as sheet piles or diaphragm walls where lowering the water table would harm nearby structures. Discharge is controlled, fine particles must not be pumped out, and uplift is checked before pumping stops.

79.What safety precautions are needed for deep excavation?

Excavation permit after checking underground utilities, safe side slopes, benching or shoring designed for the depth and soil, spoil and machines kept away from the edge, barricades and warning signs, safe ladders or ramps, dewatering, daily inspection by a competent person especially after rain, and rescue arrangements. Nobody works in an unsupported trench deeper than the safe limit.

80.What is a plate load test and what are its limits?

A plate load test (IS 1888) loads a steel plate in increments at the proposed foundation level and records settlement, giving bearing capacity and settlement characteristics of the soil just below the plate. Its limitation is that it only tests a depth of about twice the plate width, so a weak layer deeper down that a large footing would stress is not detected — it must be read with the borehole data.

81.What is the difference between total and differential settlement and why does it matter?

Total settlement is how much a foundation moves down; differential settlement is the difference in settlement between two parts of a structure. Differential settlement causes cracking, tilting and misalignment — critical for crane girders, conveyors and machinery. Codes and specifications limit both, and they are controlled by uniform bearing pressures, adequate foundation depth, piles or ground improvement and, where needed, settlement joints.

Roads, pavements and drainage in plants (6)

82.Compare flexible and rigid pavements.

A flexible (bituminous) pavement spreads load through its layers — granular sub-base, base and bituminous courses — and its design depends heavily on subgrade strength (CBR); it is cheaper initially but needs more maintenance. A rigid (concrete) pavement carries load by slab bending, spreading it over a wide area; it costs more initially but lasts long with little maintenance and suits heavy, slow and channelled traffic such as in steel plants. IRC 37 and IRC 58 are the design guidelines.

83.Explain the layers and joints of a rigid concrete pavement.

Prepared subgrade, granular sub-base with drainage layer, dry lean concrete (DLC) base with a separation membrane, and the pavement quality concrete (PQC) slab. Joints are transverse contraction joints (sawn, with dowel bars for load transfer), expansion or isolation joints where needed (with dowels and filler), construction joints, and longitudinal joints with tie bars that keep lanes together. Joints are sealed against water.

84.What is the difference between dowel bars and tie bars?

Dowel bars are plain round bars across transverse joints, one half debonded, which transfer wheel loads from one slab to the next while allowing the slabs to move freely with temperature. Tie bars are deformed bars across longitudinal joints that hold adjacent lanes together and prevent them from separating; they are not meant to transfer load by sliding. Dowels sit at mid-depth and must be parallel to the road.

85.Which tests are done during bituminous road construction?

On materials: aggregate gradation, impact value, flakiness, water absorption, and bitumen grade tests such as penetration or viscosity. During laying: mix temperature at the plant and site, binder content and gradation by extraction, Marshall properties (stability, flow, air voids), compacted density and thickness from cores, and surface regularity with a straight edge. Granular layers are checked for gradation and field density.

86.What is special about roads and hardstands in a steel plant?

They carry very heavy and slow vehicles — slag pot carriers, dumpers, ladle transfer cars, trailers with coils — often with concentrated wheel loads, spillage of hot material and oil. So heavy-duty rigid pavements or thick concrete hardstands with strong sub-base and good joint design are common, designed for the actual axle loads, with drainage and protection near hot zones.

87.How is storm water drainage planned for an industrial plant?

From the plant grading plan and rainfall intensity, the catchment areas and runoff are calculated (rational method), and a network of covered or open RCC drains is sized with self-cleansing gradients, leading to culverts, a main outfall and often a settling or oil-trap system before discharge. Roads are given camber and cross-fall towards drains, and drains are kept separate from process effluent lines.

Project planning, contracts, billing and safety (13)

88.How do you prepare a construction schedule in Primavera or MS Project?

Break the project into a work breakdown structure, list activities with durations based on quantities and productivity, link them with logic (finish-to-start and others, with lags), add resources and constraints such as material delivery and permits, calculate the critical path, and approve and save the baseline. During the project, update actual progress regularly, compare with the baseline and re-plan to recover delays.

89.What is the critical path and what is float?

The critical path is the longest chain of dependent activities from start to finish; it fixes the shortest possible project duration, and any delay on it delays completion. Float (slack) is how much an activity can be delayed without delaying the project (total float) or the next activity (free float). Critical activities have zero total float, so monitoring focuses on them.

90.Explain the S-curve and earned value terms.

An S-curve plots cumulative planned progress or cost against time; actual progress is plotted on it to see whether the project is ahead or behind. In earned value management, PV (planned value) is the budgeted cost of work scheduled, EV (earned value) the budgeted cost of work actually done, and AC (actual cost) what it really cost. SPI = EV/PV and CPI = EV/AC; values below 1 mean behind schedule or over budget.

91.How do you handle delays and extension of time?

Record every hindrance as it happens in a hindrance register — late drawings, fronts not available, material delays, weather, owner's changes — with dates and effect on activities. Analyse the impact on the critical path by comparing the baseline and updated schedules. Extension of time is granted for delays not caused by the contractor, based on this evidence; delays caused by the contractor may attract liquidated damages.

92.What are the measurement book and running account bills?

The measurement book (MB) is the authoritative record of quantities of work executed, measured jointly and signed by the engineer and the contractor with dates and locations. Running account (RA) bills are interim payments based on cumulative MB quantities at contract rates, minus previous payments, retention, recoveries for material and advances, and taxes. The final bill closes the account after completion.

93.How are extra items and deviations handled in a contract?

A deviation is a change in quantity of a BOQ item beyond the limit allowed in the contract; beyond that limit the rate may be revised as per the deviation clause. An extra item is work not in the BOQ at all; its rate is derived from similar items or analysed from market rates of material, labour and machinery plus overheads and profit. Both need written approval from the competent authority before or as the work is done.

94.What is a price variation (escalation) clause?

It adjusts the contract price for changes in the cost of inputs during execution, using a formula with fixed weightages for components such as cement, steel, bitumen, fuel, labour and other materials, applied to the change in published indices (for example RBI wholesale price indices or the Labour Bureau consumer price index) between the base date and the billing period. It protects both parties in long contracts.

95.Describe the tendering process from NIT to award.

Prepare the estimate and tender documents (scope, specifications, drawings, BOQ, conditions), publish the notice inviting tender, hold a pre-bid meeting and issue clarifications or corrigenda, receive bids (often two-part: techno-commercial and price), evaluate qualification and technical compliance, open price bids of qualified bidders, compare and negotiate if allowed, and issue the letter of award to the lowest evaluated bidder, followed by the contract agreement and performance security.

96.What is a work permit system?

It is a written control for hazardous work — hot work, work at height, confined space entry, excavation, electrical isolation, lifting. The permit states the job, the hazards, the precautions (isolation and lock-out/tag-out, gas testing, fire watch, PPE), the validity period and the people responsible, and is signed by the issuer and the receiver. Work starts only after the precautions are checked, and the permit is closed after the job.

97.What is HIRA or a job safety analysis?

HIRA (hazard identification and risk assessment) and JSA (job safety analysis) break a job into steps, identify the hazards of each step, rate the risk by likelihood and severity, and fix controls in the order elimination, substitution, engineering controls, administrative controls and PPE. They are prepared before the work, explained to the crew in a toolbox talk, and reviewed when conditions change.

98.What do you check on scaffolding before allowing people on it?

Firm base with sole plates and base plates, plumb standards, ledgers and transoms correctly coupled, bracing, ties to the structure, fully boarded platforms, guard rails and toe boards, safe access ladders, load limits displayed, and no damaged tubes or couplers. A competent person inspects it and puts a green 'safe to use' tag; it is re-inspected regularly and after bad weather. IS 3696 covers scaffold safety.

99.What goes into a monthly progress report for the client?

Overall and area-wise physical progress against plan (with S-curve), key milestones achieved and missed, look-ahead for next month, manpower and machinery deployed, quality status (tests, NCRs open and closed), safety statistics (man-hours, incidents), drawing and material status, hindrances and their impact, billing and cash flow, risks and decisions needed from the client, and photographs.

100.The schedule is tight and the contractor wants to skip a quality step. What will you do?

I will not allow it. A skipped check in RCC or steel work can mean a defect that costs far more time to repair later, or a safety failure. Instead I will help recover time in other ways — planning inspections in advance so they never hold the work, extra shifts or resources, resequencing activities — and record the situation. Quality and safety requirements in the contract are not negotiable at site level.

Prepared by CIVILGYAN for this recruitment, checked 2026-10-11. Answers follow standard practice and the IS codes named; always confirm project-specific values against the code edition and specification you work with.

FAQs — MECON Limited – Engineer posts (Civil, Civil & Structural and others) on Fixed Tenure – 159 posts

What is the last date to apply for MECON Limited – Engineer posts (Civil, Civil & Structural and others) on Fixed Tenure – 159 posts?

Online application: 03.10.2026 to 17.10.2026

Who can apply for MECON Limited – Engineer posts (Civil, Civil & Structural and others) on Fixed Tenure – 159 posts?

Needs work experience. Every post asks for post-qualification work experience — at least 2 years for Assistant Engineer, 5 years for Deputy Engineer and 9 to 10 years for Additional Engineer. Fresh graduates cannot apply. Qualification: B.E./B.Tech in Civil Engineering (some Civil & Structural posts also take Mechanical; one Deputy Engineer (Civil) post also takes a Civil diploma with 10 years' experience) plus post-qualification experience of 2 to 10 years, by post.

What is the selection process for MECON Limited – Engineer posts (Civil, Civil & Structural and others) on Fixed Tenure – 159 posts?

Selection is by interview only — there is no written test, so there is no syllabus to study for.

What is the salary for MECON Limited – Engineer posts (Civil, Civil & Structural and others) on Fixed Tenure – 159 posts?

Consolidated ₹45,050 (Assistant Engineer), ₹54,990 (Deputy Engineer), ₹67,860 (Additional Engineer) a month, plus site allowance 7.5% and other benefits

How to apply for MECON Limited – Engineer posts (Civil, Civil & Structural and others) on Fixed Tenure – 159 posts?

Apply online only, at MECON's website: Careers → Career Opportunities → Apply Online. Upload a photograph and signature (JPG, up to 40 KB each) and all certificates as one self-attested PDF of up to 1 MB: age proof, degree and all mark sheets, experience proofs, PAN and Aadhaar (Aadhaar is mandatory), and category/PwD/ex-servicemen certificates where applicable. Employees of government, PSUs or autonomous bodies must apply through proper channel or bring a No Objection Certificate to the interview. Bring all original documents and a hard copy of the online application to the interview; queries go to recruit@meconlimited.co.in.

Where is the official notification PDF of MECON Limited – Engineer posts (Civil, Civil & Structural and others) on Fixed Tenure – 159 posts?

The complete notification is on this page under 'Official Notification PDF' — open it on the page or download it.